Steel Reinforcement unit price, Alabama

Low bidders on ALDOT contracts carried a median of $1.96 per LB for item 502A000, steel reinforcement, over the 24 months to 28 AUG 2026, across 46 low bids. Half of all 160 bids fell between $1.54 and $3.75.

Owner
Alabama DOT
Item
502A000
Unit
LB
Latest letting
28 AUG 2026
$1.96Low bidder's median, per LB
$2.17Median of all bids, per LB
46Contracts in the window

By year of letting

Steel Reinforcement, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221919$1.9569$1.85
20232828$1.7984$2.00
20242828$1.9085$1.94
20252222$1.9174$1.88
20261010$2.2142$3.12
Steel Reinforcement, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Steel Reinforcement, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
03017$1.8725$1.96
05024$4.5517$4.00
02023$1.6213$1.68
01053$1.4613$1.57
03053$1.499$1.49
09013$1.598$2.40
Steel Reinforcement, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Steel Reinforcement, ALDOT: low bidder's median by quantity band
Quantity (LB)Low bidsLow-bid median
50 to 2,33111$7.69
3,859 to 20,12412$1.98
26,900 to 47,74311$1.95
50,800 to 1,608,64512$1.55
Steel Reinforcement, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Steel Reinforcement
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 2026202608280040502744$8.40$4.506IVS HYDRO, INC.ALDOT
28 AUG 20262026082801104023,859$2.30$3.224VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
31 JUL 2026202607310080802910$7.69$8.854PL RUSSELL LLCALDOT
31 JUL 202620260731022010513,264$2.17$2.175LAMBERT CONTRACTING, LLCALDOT
29 MAY 2026202605290010603328,465$3.43$3.263APAC-ALABAMA, INC.ALDOT
24 APR 202620260424001070450$1.21$7.504F&W CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 2026202603270010606156,100$2.26$1.922NEWELL & BUSH, INC.ALDOT
27 FEB 20262026022702807021,110$2.10$4.005S. A. GRAHAM COMPANY, INC.ALDOT
30 JAN 20262026013000101059,600$1.20$1.336ROGERS GROUP, INC.ALDOT
30 JAN 2026202601300030504160,400$1.43$1.453MCINNIS CONSTRUCTION, LLCALDOT
05 DEC 202520251205002020115,400$1.50$1.503MILLER & MILLER, INC.ALDOT
05 DEC 202520251205003090150,800$1.59$1.594MCINNIS CONSTRUCTION, LLCALDOT
05 DEC 202520251205014060493$11.50$11.501APAC-ALABAMA, INC.ALDOT
05 DEC 2025202512050210103717$10.84$10.003WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
07 NOV 20252025110705708041,480$2.50$4.008PINE CITY CONTRACTING, LLCALDOT
Latest ALDOT contracts carrying Steel Reinforcement

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy