Furnishing and installing precast concrete barrier unit price, Arkansas
Low bidders on ARDOT contracts carried a median of $56.86 per LF for item 604031, furnishing and installing precast concrete barrier, over the 24 months to 04 NOV 2026, across 28 low bids. Half of all 105 bids fell between $50.00 and $75.00.
- Owner
- Arkansas DOT
- Item
- 604031
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 22 | 22 | $64.50 | 61 | $65.00 |
| 2023 | 30 | 30 | $76.75 | 68 | $75.56 |
| 2024 | 34 | 34 | $66.00 | 76 | $66.50 |
| 2025 | 12 | 12 | $66.62 | 42 | $64.62 |
| 2026 | 13 | 13 | $52.81 | 54 | $58.91 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 133 to 405 | 7 | $75.00 |
| 433 to 746 | 7 | $53.50 |
| 872 to 1,640 | 7 | $60.00 |
| 2,006 to 14,257 | 7 | $46.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | 040904 | Crawford | 14,257 | $44.21 | $45.61 | 4 | CROSSLAND CONSTRUCTION CO., INC. | ARDOT |
| 04 NOV 2026 | 050439 | Independence | 1,092 | $40.00 | $46.00 | 5 | WHITE RIVER MATERIALS, INC. | ARDOT |
| 04 NOV 2026 | 101141 | Mississippi | 133 | $231.00 | $110.00 | 4 | BLUFF CITY CONSTRUCTION CO., LLC | ARDOT |
| 23 SEP 2026 | 061938 | Pulaski | 4,019 | $34.61 | $42.30 | 2 | COLLINS & HERMANN, INC. | ARDOT |
| 23 SEP 2026 | 070458 | Columbia | 632 | $53.72 | $53.72 | 7 | MOBLEY CONTRACTORS, INC. | ARDOT |
| 12 AUG 2026 | 030531 | Little River | 433 | $53.00 | $72.00 | 6 | MCGEORGE CONTRACTING CO., INC. | ARDOT |
| 12 AUG 2026 | 012535 | Conway, Faulkner, Pulaski | 746 | $82.00 | $82.00 | 1 | CREATIVE DESIGN CONCEPTS, INC. | ARDOT |
| 20 MAY 2026 | 020802 | Jefferson | 519 | $47.60 | $54.60 | 5 | 1911 CONSTRUCTION COMPANY, INC. | ARDOT |
| 04 MAR 2026 | 101003 | Randolph | 2,006 | $46.00 | $58.54 | 5 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 04 MAR 2026 | 101100 | Greene | 1,640 | $29.25 | $34.48 | 4 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 04 MAR 2026 | A00096 | Craighead, Greene | 200 | $52.81 | $66.62 | 4 | ATLAS ASPHALT, INC. | ARDOT |
| 21 JAN 2026 | 061371 | Lonoke | 8,495 | $88.45 | $69.22 | 4 | WEAVER-BAILEY CONTRACTORS, INC. | ARDOT |
| 21 JAN 2026 | 100881 | Craighead | 186 | $75.00 | $75.00 | 3 | ROGERS GROUP, INC. | ARDOT |
| 05 NOV 2025 | 090651 | Benton | 140 | $114.00 | $60.30 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
| 15 OCT 2025 | 040746 | Washington | 1,540 | $60.00 | $64.25 | 3 | APAC-CENTRAL, INC. | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.