Low bidders on ARDOT contracts carried a median of $5.23 per LF for item 718005, reflectorized paint pavement marking white (12"), over the 24 months to 04 NOV 2026, across 27 low bids. Half of all 82 bids fell between $4.00 and $10.23.
- Owner
- Arkansas DOT
- Item
- 718005
- Unit
- LF
- Latest letting
- 20 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 9 | 9 | $8.00 | 14 | $6.75 |
| 2023 | 21 | 21 | $6.00 | 42 | $5.90 |
| 2024 | 15 | 15 | $5.50 | 31 | $5.50 |
| 2025 | 18 | 18 | $5.97 | 54 | $5.35 |
| 2026 | 7 | 7 | $5.15 | 24 | $7.50 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 21 to 60 | 6 | $11.21 |
| 70 to 200 | 7 | $6.00 |
| 220 to 368 | 7 | $5.00 |
| 392 to 2,302 | 7 | $5.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 MAY 2026 | 020802 | Jefferson | 55 | $11.20 | $20.00 | 5 | 1911 CONSTRUCTION COMPANY, INC. | ARDOT |
| 08 APR 2026 | C76092 | Hot Spring, Saline | 60 | $5.15 | $5.00 | 3 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 04 MAR 2026 | A90038 | Searcy | 392 | $5.04 | $5.02 | 2 | APAC-CENTRAL, INC. | ARDOT |
| 04 MAR 2026 | A00096 | Craighead, Greene | 21 | $4.00 | $4.10 | 4 | ATLAS ASPHALT, INC. | ARDOT |
| 21 JAN 2026 | C04029 | Benton | 60 | $11.21 | $10.76 | 4 | EMERY SAPP & SONS, INC. | ARDOT |
| 21 JAN 2026 | C42007 | Logan | 220 | $7.00 | $7.50 | 4 | BLACKSTONE CONSTRUCTION, LLC | ARDOT |
| 21 JAN 2026 | C60015 | Pulaski | 690 | $0.90 | $0.90 | 2 | CRANFORD CONSTRUCTION CO. | ARDOT |
| 05 NOV 2025 | A20023 | Drew | 368 | $4.00 | $3.58 | 2 | PINE BLUFF SAND & GRAVEL CO. | ARDOT |
| 05 NOV 2025 | A40053 | Franklin | 50 | $11.33 | $10.83 | 5 | EMERY SAPP & SONS, INC. | ARDOT |
| 05 NOV 2025 | 090433 | Benton | 276 | $3.50 | $3.57 | 4 | GRANT GARRETT EXCAVATING, INC. | ARDOT |
| 15 OCT 2025 | 040746 | Washington | 422 | $3.40 | $3.40 | 3 | APAC-CENTRAL, INC. | ARDOT |
| 17 SEP 2025 | 061510 | Pulaski | 342 | $5.23 | $4.99 | 2 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 13 AUG 2025 | 020628 | Jefferson | 2,302 | $3.32 | $3.42 | 2 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 25 JUN 2025 | 100879 | Craighead | 464 | $8.00 | $7.75 | 4 | ROGERS GROUP, INC. | ARDOT |
| 21 MAY 2025 | C32005 | Independence | 178 | $6.00 | $6.00 | 1 | WHITE RIVER MATERIALS, INC. | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.