Removal of permanent pavement markings unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $1.06 per LF for item 604061, removal of permanent pavement markings, over the 24 months to 04 NOV 2026, across 48 low bids. Half of all 170 bids fell between $0.50 and $1.35.

Owner
Arkansas DOT
Item
604061
Unit
LF
Latest letting
04 NOV 2026
$1.06Low bidder's median, per LF
$1.00Median of all bids, per LF
48Contracts in the window

By year of letting

Removal of permanent pavement markings, ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221919$1.0549$1.05
20231616$1.5438$1.58
20242424$1.5053$1.42
20251717$1.2659$1.22
20263030$0.90109$0.65
Removal of permanent pavement markings, ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Removal of permanent pavement markings, ARDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Crawford4$0.9514$0.49
Pulaski3$1.387$1.38
Removal of permanent pavement markings, ARDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Removal of permanent pavement markings, ARDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
95 to 1,42012$1.45
1,500 to 3,20012$1.02
3,222 to 7,68612$1.10
8,144 to 55,91812$0.66
Removal of permanent pavement markings, ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying Removal of permanent pavement markings
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026A10059Phillips522$1.10$1.101ATLAS ASPHALT, INC.ARDOT
04 NOV 2026040904Crawford3,222$3.25$3.234CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026A50033White1,525$0.80$0.803CK ASPHALT, LLCARDOT
04 NOV 2026061922Garland4,375$4.40$4.402TI-ZACK CONCRETE, LLCARDOT
04 NOV 2026A90050Baxter14,108$0.32$0.362ATLAS ASPHALT, INC.ARDOT
23 SEP 2026061921Pulaski1,625$1.38$1.383TI-ZACK CONCRETE, LLCARDOT
23 SEP 2026061938Pulaski700$1.61$3.962COLLINS & HERMANN, INC.ARDOT
23 SEP 2026070458Columbia7,686$1.05$1.057MOBLEY CONTRACTORS, INC.ARDOT
23 SEP 2026012559Craighead, Crittenden4,555$1.15$1.172SHELBY ELECTRIC COMPANY, INC.ARDOT
12 AUG 2026030531Little River8,644$1.98$2.086MCGEORGE CONTRACTING CO., INC.ARDOT
12 AUG 2026012535Conway, Faulkner, Pulaski11,189$6.00$6.001CREATIVE DESIGN CONCEPTS, INC.ARDOT
24 JUN 2026101189Craighead3,300$0.19$0.302WHITE RIVER MATERIALS, INC.ARDOT
08 APR 2026110751Lee1,680$0.17$0.208WHITE RIVER MATERIALS, INC.ARDOT
08 APR 2026110831Cross15,200$0.67$0.197JAMES A. ROGERS EXCAVATING, INC.ARDOT
08 APR 2026110832Cross3,440$0.35$0.398WHITE RIVER MATERIALS, INC.ARDOT
Latest ARDOT contracts carrying Removal of permanent pavement markings

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy