Silicone joint sealant unit price, Arkansas
Low bidders on ARDOT contracts carried a median of $95.00 per LF for item 809015, silicone joint sealant, over the 24 months to 04 NOV 2026, across 11 low bids. Half of all 47 bids fell between $92.28 and $146.43.
- Owner
- Arkansas DOT
- Item
- 809015
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 19 | 19 | $75.00 | 52 | $72.00 |
| 2023 | 17 | 17 | $75.00 | 32 | $85.00 |
| 2024 | 15 | 15 | $85.00 | 34 | $92.00 |
| 2025 | 7 | 7 | $105.00 | 31 | $125.00 |
| 2026 | 3 | 3 | $78.75 | 13 | $95.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | 040904 | Crawford | 171 | $51.89 | $97.16 | 4 | CROSSLAND CONSTRUCTION CO., INC. | ARDOT |
| 04 NOV 2026 | BR4401 | Madison | 62 | $95.00 | $100.00 | 5 | WEST PLAINS BR. & GRADING, LLC | ARDOT |
| 21 JAN 2026 | 061371 | Lonoke | 452 | $78.75 | $61.88 | 4 | WEAVER-BAILEY CONTRACTORS, INC. | ARDOT |
| 05 NOV 2025 | 110747 | Monroe, St. Francis | 87 | $225.00 | $237.50 | 4 | REDSTONE CONSTRUCTION GROUP, INC. | ARDOT |
| 05 NOV 2025 | 090672 | Searcy | 141 | $100.00 | $128.27 | 6 | CROUSE CONSTRUCTION CO. | ARDOT |
| 17 SEP 2025 | 070509 | Clark | 260 | $105.00 | $104.35 | 6 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 25 JUN 2025 | 061745 | Lonoke | 79 | $120.00 | $106.37 | 3 | THOMCO, INC. | ARDOT |
| 21 MAY 2025 | 110861 | Cross | 58 | $80.00 | $150.00 | 3 | DEMENT CONSTRUCTION CO., LLC | ARDOT |
| 21 MAY 2025 | 040866 | Washington | 70 | $28.00 | $146.44 | 6 | CROSSLAND CONSTRUCTION CO., INC. | ARDOT |
| 15 JAN 2025 | 100995 | Craighead | 66 | $105.00 | $106.74 | 3 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 06 NOV 2024 | 101017 | Poinsett | 128 | $92.00 | $127.00 | 3 | ROBERTSON CONTRACTORS, INC. | ARDOT |
| 18 SEP 2024 | 110715 | Lee, Monroe | 86 | $162.00 | $139.90 | 2 | CAPITAL PAVING & CONSTRUCTION, LLC | ARDOT |
| 18 SEP 2024 | 040792 | Sebastian | 104 | $35.00 | $84.89 | 2 | ROBINSON CONSTRUCTION, LLC | ARDOT |
| 18 SEP 2024 | 061741 | Hot Spring | 74 | $77.94 | $131.53 | 2 | KIEWIT INFRASTRUCTURE SOUTH CO. | ARDOT |
| 18 SEP 2024 | 101172 | Clay | 66 | $76.00 | $73.00 | 4 | KOSS CONSTRUCTION CO. | ARDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.
How these prices were read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.