Temporary impact attenuation barrier unit price, Arkansas

Low bidders on ARDOT contracts carried a median of $7,144.50 per EACH for item 731071, temporary impact attenuation barrier, over the 24 months to 04 NOV 2026, across 24 low bids. Half of all 90 bids fell between $5,378.03 and $9,955.00.

Owner
Arkansas DOT
Item
731071
Unit
EACH
Latest letting
04 NOV 2026
$7,144.50Low bidder's median, per EACH
$7,779.28Median of all bids, per EACH
24Contracts in the window

By year of letting

Temporary impact attenuation barrier, ARDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221515$5,500.0042$5,500.00
20232222$6,225.0049$6,150.00
20243030$5,650.0066$5,645.32
20251010$8,450.0035$7,957.00
20261111$6,000.0046$7,629.28
Temporary impact attenuation barrier, ARDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Temporary impact attenuation barrier, ARDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 26$7,400.00
2 to 26$6,650.00
2 to 36$8,413.90
4 to 226$5,887.70
Temporary impact attenuation barrier, ARDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ARDOT contracts carrying Temporary impact attenuation barrier
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
04 NOV 2026040904Crawford22$11,896$9,702.004CROSSLAND CONSTRUCTION CO., INC.ARDOT
04 NOV 2026050439Independence3$2,718.76$11,1695WHITE RIVER MATERIALS, INC.ARDOT
04 NOV 2026101141Mississippi1$6,300.00$6,650.004BLUFF CITY CONSTRUCTION CO., LLCARDOT
23 SEP 2026061938Pulaski3$8,609.80$16,8052COLLINS & HERMANN, INC.ARDOT
12 AUG 2026030531Little River1$6,000.00$11,6706MCGEORGE CONTRACTING CO., INC.ARDOT
20 MAY 2026020802Jefferson1$8,960.00$10,50051911 CONSTRUCTION COMPANY, INC.ARDOT
04 MAR 2026101003Randolph2$5,000.00$5,500.005ROBERTSON CONTRACTORS, INC.ARDOT
04 MAR 2026101100Greene4$4,000.00$4,600.004ROBERTSON CONTRACTORS, INC.ARDOT
04 MAR 2026A00096Craighead, Greene2$5,357.94$6,853.974ATLAS ASPHALT, INC.ARDOT
21 JAN 2026061371Lonoke11$5,250.00$5,185.004WEAVER-BAILEY CONTRACTORS, INC.ARDOT
21 JAN 2026100881Craighead3$23,000$9,500.973ROGERS GROUP, INC.ARDOT
05 NOV 2025090651Benton2$9,588.00$8,919.004GRANT GARRETT EXCAVATING, INC.ARDOT
15 OCT 2025040746Washington3$8,218.00$9,419.693APAC-CENTRAL, INC.ARDOT
17 SEP 2025040889Sebastian5$8,400.00$13,4782FORSGREN, INC.ARDOT
17 SEP 2025090647Baxter1$8,500.00$9,735.676CROUSE CONSTRUCTION CO.ARDOT
Latest ARDOT contracts carrying Temporary impact attenuation barrier

Filter this item by your own quantity, county and period, or check your price against it, in the ARDOT explorer.

How these prices were read

ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ARDOT's own: this item is compared with ARDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy