Bridge deck expansion joint, rehabilitation, poured joint backer rod unit price, Florida

Low bidders on FDOT contracts carried a median of $84.67 per LF for item 0458-1-21, bridge deck expansion joint, rehabilitation, poured joint backer rod, over the 24 months to 28 OCT 2026, across 47 low bids. Half of all 184 bids fell between $69.00 and $113.50.

Owner
Florida DOT
Item
0458-1-21
Unit
LF
Latest letting
28 OCT 2026
$84.67Low bidder's median, per LF
$83.69Median of all bids, per LF
47Contracts in the window

By year of letting

Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201877$50.0027$58.63
20191010$55.0037$75.00
20201515$52.0063$53.90
20211212$57.5066$56.00
20222222$70.3756$72.25
20232828$83.8383$79.40
20241818$104.4071$92.00
20252020$83.9268$84.84
20262121$75.0094$80.00
Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 226$81.69100$82.50
District 46$68.5029$75.00
District 37$99.4920$109.75
District 73$100.0016$91.24
District 13$62.1311$62.13
Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
29 to 7211$120.00
80 to 26412$84.80
282 to 54012$63.56
570 to 3,52012$75.27
Bridge deck expansion joint, rehabilitation, poured joint backer rod, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Bridge deck expansion joint, rehabilitation, poured joint backer rod
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 1282$52.28$55.454AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A73District 2570$64.00$78.538C.W. ROBERTS CONTRACTING, INC.FDOT
28 OCT 2026T2A86District 2644$62.25$63.058PIGOTT ASPHALT AND SITEWORK LLCFDOT
28 OCT 2026T2B08District 235$92.68$92.681ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T4765District 4480$77.00$80.376GENERAL ASPHALT COMPANY, LLCFDOT
30 SEP 2026T2A80District 2352$80.20$80.003ANDERSON COLUMBIA CO., INC.FDOT
26 AUG 2026T2A75District 264$86.00$108.495PREFERRED MATERIALS INC.FDOT
26 AUG 2026T2A77District 2328$65.00$70.043PEAVY & SON CONSTRUCTION CO., INC.FDOT
26 AUG 2026T2A78District 2221$75.00$75.003DUVAL ASPHALT PRODUCTS, INC.FDOT
26 AUG 2026T3998District 3600$72.89$91.303ANDERSON COLUMBIA CO., INC.FDOT
26 AUG 2026T7614District 730$100.00$87.816PIGOTT ASPHALT AND SITEWORK LLCFDOT
29 JUL 2026T7619District 756$271.48$175.006TURTLE INFRASTRUCTURE PARTNERS, LLCFDOT
10 JUN 2026T2A50District 2196$104.35$104.353ANDERSON COLUMBIA CO., INC.FDOT
29 APR 2026T4738District 4540$46.00$70.557OHLA USA INCFDOT
25 MAR 2026T1919District 1990$99.08$55.124AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
Latest FDOT contracts carrying Bridge deck expansion joint, rehabilitation, poured joint backer rod

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy