Commercial material for temporary driveway maintenance unit price, Florida
Low bidders on FDOT contracts carried a median of $100.00 per CY for item 0102-3, commercial material for temporary driveway maintenance, over the 24 months to 28 OCT 2026, across 59 low bids. Half of all 274 bids fell between $80.66 and $250.00.
- Owner
- Florida DOT
- Item
- 0102-3
- Unit
- CY
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 40 | 40 | $43.10 | 188 | $50.00 |
| 2019 | 39 | 38 | $55.40 | 173 | $58.12 |
| 2020 | 28 | 28 | $49.28 | 136 | $58.75 |
| 2021 | 41 | 40 | $75.00 | 192 | $56.50 |
| 2022 | 37 | 36 | $123.68 | 135 | $108.00 |
| 2023 | 44 | 44 | $114.90 | 154 | $114.90 |
| 2024 | 42 | 41 | $108.60 | 149 | $145.00 |
| 2025 | 28 | 28 | $100.00 | 130 | $137.81 |
| 2026 | 24 | 23 | $100.00 | 119 | $114.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 3 | 24 | $100.00 | 90 | $125.00 |
| District 5 | 9 | $105.00 | 58 | $148.10 |
| District 1 | 7 | $66.07 | 33 | $115.15 |
| District 7 | 6 | $129.00 | 32 | $125.91 |
| District 4 | 6 | $73.80 | 27 | $146.00 |
| District 6 | 3 | $88.00 | 21 | $100.00 |
| District 2 | 4 | $436.11 | 13 | $212.40 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 18.40 | 14 | $261.70 |
| 19 to 41.20 | 15 | $100.74 |
| 47.60 to 144.40 | 15 | $88.00 |
| 149 to 1,040.90 | 15 | $62.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T2B08 | District 2 | 10 | $499.41 | $499.41 | 1 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 30 SEP 2026 | T2A81 | District 2 | 7.60 | $372.80 | $372.80 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 30 SEP 2026 | T3937 | District 3 | 41.20 | $75.00 | $100.00 | 4 | MURPHREE BRIDGE CORPORATION | FDOT |
| 26 AUG 2026 | T1948 | District 1 | 72.90 | $65.00 | $57.50 | 10 | LEON AMERICA CONSTRUCTION | FDOT |
| 26 AUG 2026 | T3A32 | District 3 | 99.30 | $52.95 | $52.95 | 5 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 26 AUG 2026 | T5890 | District 5 | 71.50 | $110.00 | $139.50 | 6 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 29 JUL 2026 | T3A03 | District 3 | 38.70 | $50.25 | $53.00 | 5 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 29 JUL 2026 | T4745 | District 4 | 30.10 | $189.04 | $225.00 | 6 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
| 10 JUN 2026 | T3952 | District 3 | 13.90 | $188.72 | $144.36 | 2 | RJ GORMAN CONTRACTING LLC | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 149 | $45.00 | $78.11 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 APR 2026 | T7562 | District 7 | 68.70 | $320.00 | $200.00 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 31 MAR 2026 | T3845 | District 3 | 900 | $50.00 | $80.00 | 4 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 25 MAR 2026 | T1919 | District 1 | 245.80 | $66.07 | $75.03 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 6.40 | $350.00 | $450.00 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T3939 | District 3 | 25.50 | $100.74 | $100.74 | 3 | RJ GORMAN CONTRACTING LLC | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.