Conduit, furnish & install, mount unit price, Florida
Low bidders on FDOT contracts carried a median of $55.00 per LF for item 0630-2-15, conduit, furnish & install, mount, over the 24 months to 28 OCT 2026, across 23 low bids. Half of all 127 bids fell between $45.00 and $76.07.
- Owner
- Florida DOT
- Item
- 0630-2-15
- Unit
- LF
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 15 | 16 | $20.71 | 90 | $22.00 |
| 2019 | 10 | 11 | $31.17 | 37 | $31.17 |
| 2020 | 8 | 9 | $33.70 | 66 | $30.00 |
| 2021 | 11 | 12 | $28.95 | 55 | $29.00 |
| 2022 | 12 | 13 | $45.00 | 51 | $46.00 |
| 2023 | 13 | 16 | $55.63 | 61 | $50.21 |
| 2024 | 9 | 9 | $70.00 | 40 | $75.94 |
| 2025 | 15 | 16 | $55.27 | 83 | $56.09 |
| 2026 | 6 | 7 | $55.00 | 44 | $48.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 11 | $55.00 | 67 | $52.00 |
| District 5 | 4 | $56.90 | 23 | $58.00 |
| District 6 | 3 | $71.00 | 15 | $71.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 54 to 240 | 5 | $55.00 |
| 255 to 353 | 6 | $59.00 |
| 354 to 492 | 6 | $60.50 |
| 500 to 3,582 | 6 | $53.03 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T6398 | District 6 | 200 | $71.00 | $74.10 | 4 | OHLA USA INC | FDOT |
| 30 SEP 2026 | T6398 | District 6 | 640 | $71.00 | $74.10 | 4 | OHLA USA INC | FDOT |
| 26 AUG 2026 | T4757 | District 4 | 331 | $24.43 | $46.90 | 12 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 520 | $60.91 | $14.87 | 8 | OHLA USA INC | FDOT |
| 25 MAR 2026 | T5876 | District 5 | 54 | $47.31 | $46.41 | 6 | TIMOTHY ROSE CONTRACTING, INC. | FDOT |
| 25 MAR 2026 | T6591 | District 6 | 492 | $55.00 | $49.40 | 7 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 28 JAN 2026 | T4749 | District 4 | 1,206 | $42.35 | $42.35 | 3 | CONE & GRAHAM, INC. | FDOT |
| 03 DEC 2025 | T4729 | District 4 | 255 | $70.25 | $75.62 | 8 | WEBBER, LLC | FDOT |
| 30 JUL 2025 | T1921 | District 1 | 356 | $127.72 | $48.46 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 30 JUL 2025 | T4674 | District 4 | 472 | $66.00 | $65.00 | 4 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 30 JUL 2025 | T4736 | District 4 | 500 | $87.00 | $99.00 | 7 | PRINCE CONTRACTING, LLC. | FDOT |
| 30 JUL 2025 | T7574 | District 7 | 3,582 | $45.16 | $55.12 | 6 | TRAFFIC MANAGEMENT SOLUTIONS, LLC | FDOT |
| 11 JUN 2025 | T5856 | District 5 | 269 | $362.00 | $143.00 | 5 | TRAFFIC CONTROL DEVICES, LLC | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 354 | $29.00 | $29.90 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 28 MAY 2025 | T5854 | District 5 | 430 | $49.80 | $51.63 | 5 | JR. DAVIS CONSTRUCTION CO., INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.