Inlets, dt bot, type c, modify unit price, Florida
Low bidders on FDOT contracts carried a median of $8,050.00 per EACH for item 0425-1529, inlets, dt bot, type c, modify, over the 24 months to 28 OCT 2026, across 7 low bids. Half of all 37 bids fell between $5,594.17 and $9,000.00.
- Owner
- Florida DOT
- Item
- 0425-1529
- Unit
- EACH
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 6 | 6 | $4,150.00 | 30 | $4,234.66 |
| 2019 | 10 | 10 | $3,724.14 | 50 | $3,904.14 |
| 2020 | 3 | 3 | $3,300.00 | 18 | $4,200.00 |
| 2021 | 8 | 8 | $4,418.25 | 49 | $4,893.54 |
| 2022 | 8 | 8 | $6,449.49 | 30 | $5,732.57 |
| 2023 | 7 | 7 | $8,516.99 | 20 | $9,300.00 |
| 2024 | 4 | 4 | $7,460.88 | 13 | $9,000.00 |
| 2025 | 4 | 4 | $8,325.00 | 23 | $7,000.00 |
| 2026 | 2 | 2 | $10,961 | 12 | $7,400.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 1 | 10 | $4,050.00 | 53 | $4,200.00 |
| District 4 | 7 | $4,600.00 | 51 | $5,069.52 |
| District 5 | 9 | $4,943.45 | 42 | $6,416.50 |
| District 7 | 7 | $5,444.50 | 34 | $4,555.22 |
| District 3 | 8 | $6,560.49 | 24 | $6,560.49 |
| District 2 | 7 | $5,500.00 | 23 | $5,001.00 |
| District 6 | 3 | $6,800.00 | 16 | $6,900.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 13 | $4,700.00 |
| 1 to 1 | 13 | $8,321.76 |
| 2 to 2 | 13 | $4,100.00 |
| 3 to 55 | 13 | $4,610.44 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T6398 | District 6 | 49 | $5,322.50 | $7,979.22 | 4 | OHLA USA INC | FDOT |
| 10 JUN 2026 | T5888 | District 5 | 6 | $16,600 | $7,400.00 | 8 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 29 OCT 2025 | T1917 | District 1 | 2 | $10,000 | $5,552.30 | 4 | OHLA USA INC | FDOT |
| 30 JUL 2025 | T5819 | District 5 | 1 | $8,050.00 | $7,051.02 | 8 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 11 JUN 2025 | T3852 | District 3 | 2 | $4,500.00 | $5,143.26 | 6 | AMERICAN SAND & X-CAVATION, INC. DBA AMERICAN SAND & ASPHALT | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 1 | $8,600.00 | $9,000.00 | 5 | MASTEC CIVIL LLC | FDOT |
| 04 DEC 2024 | T3931 | District 3 | 3 | $6,600.00 | $7,980.63 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 19 JUN 2024 | T7501 | District 7 | 1 | $8,321.76 | $11,000 | 4 | WEBBER, LLC | FDOT |
| 22 MAY 2024 | T1865 | District 1 | 1 | $14,164 | $14,164 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 22 MAY 2024 | T4655 | District 4 | 11 | $4,600.00 | $4,850.00 | 4 | OHLA USA INC | FDOT |
| 15 NOV 2023 | T1866 | District 1 | 1 | $10,500 | $10,000 | 5 | MJC LAND DEVELOPMENT, LLC | FDOT |
| 13 SEP 2023 | T6413 | District 6, Turnpike | 1 | $5,300.00 | $7,150.00 | 2 | GGI CONSTRUCTORS JV | FDOT |
| 14 JUN 2023 | T2921 | District 2 | 2 | $8,516.99 | $9,554.35 | 2 | PREFERRED MATERIALS INC. | FDOT |
| 14 JUN 2023 | T3841 | District 3 | 1 | $15,024 | $19,119 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 24 MAY 2023 | T7462 | District 7 | 2 | $8,500.00 | $8,500.00 | 3 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.