Load center, rework, voltage unit price, Florida
Low bidders on FDOT contracts carried a median of $2,687.89 per EACH for item 0715-7-21, load center, rework, voltage, over the 24 months to 28 OCT 2026, across 12 low bids. Half of all 56 bids fell between $2,056.26 and $4,755.13.
- Owner
- Florida DOT
- Item
- 0715-7-21
- Unit
- EACH
- Latest letting
- 29 APR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 7 | 7 | $1,650.00 | 38 | $2,459.60 |
| 2019 | 5 | 5 | $1,017.24 | 25 | $1,017.24 |
| 2020 | 9 | 9 | $1,500.00 | 67 | $1,700.00 |
| 2021 | 6 | 6 | $1,724.50 | 31 | $1,953.15 |
| 2022 | 7 | 7 | $4,780.00 | 25 | $4,780.00 |
| 2023 | 4 | 4 | $5,429.27 | 12 | $4,059.27 |
| 2024 | 13 | 13 | $3,065.11 | 43 | $3,311.86 |
| 2025 | 7 | 7 | $3,125.09 | 37 | $3,700.00 |
| 2026 | 3 | 3 | $1,719.64 | 14 | $1,753.12 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $3,500.00 |
| 1 to 1 | 3 | $5,400.00 |
| 1 to 1 | 3 | $2,520.00 |
| 2 to 4 | 3 | $2,108.34 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 APR 2026 | T4738 | District 4 | 2 | $2,108.34 | $2,108.34 | 7 | OHLA USA INC | FDOT |
| 25 MAR 2026 | T2A65 | District 2 | 4 | $892.00 | $1,610.18 | 2 | AMERICAN LIGHTING AND SIGNALIZATION, LLC. | FDOT |
| 25 FEB 2026 | T1916 | District 1 | 1 | $1,719.64 | $1,719.64 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 03 DEC 2025 | T7559 | District 7 | 1 | $5,400.00 | $5,003.33 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 29 OCT 2025 | T4743 | District 4 | 3 | $2,574.52 | $4,369.74 | 10 | SICE INC | FDOT |
| 27 AUG 2025 | T4715 | District 4 | 1 | $3,500.00 | $3,700.00 | 9 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&E | FDOT |
| 30 JUL 2025 | T4674 | District 4 | 1 | $6,465.80 | $4,035.00 | 4 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 30 JUL 2025 | T4720 | District 4 | 1 | $2,520.00 | $2,520.00 | 3 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 28 MAY 2025 | T2A20 | District 2 | 1 | $3,125.09 | $3,125.09 | 1 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 26 FEB 2025 | T4712 | District 4 | 1 | $2,801.26 | $3,000.00 | 5 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 04 DEC 2024 | T3931 | District 3 | 1 | $12,000 | $11,940 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 30 OCT 2024 | T7517 | District 7 | 1 | $748.23 | $640.00 | 3 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 31 JUL 2024 | T3862 | District 3 | 1 | $6,200.00 | $6,825.36 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 31 JUL 2024 | T3901 | District 3 | 1 | $5,140.53 | $4,375.70 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 12 JUN 2024 | T3915 | District 3 | 1 | $3,065.11 | $3,900.00 | 3 | GOSALIA CONCRETE CONSTRUCTORS, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.