Midblock crosswalk: hybrid beacon assembly, & install complete assembly unit price, Florida

Low bidders on FDOT contracts carried a median of $2,255.00 per AS for item 0654-3-10, midblock crosswalk: hybrid beacon assembly, & install complete assembly, over the 24 months to 28 OCT 2026, across 17 low bids. Half of all 67 bids fell between $2,038.29 and $2,625.45.

Owner
Florida DOT
Item
0654-3-10
Unit
AS
Latest letting
26 AUG 2026
$2,255.00Low bidder's median, per AS
$2,300.00Median of all bids, per AS
17Contracts in the window

By year of letting

Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202155$1,300.0017$1,304.91
202288$1,974.8432$2,000.00
202388$2,224.8621$2,118.37
20241313$2,175.3444$2,277.77
202566$2,204.6325$2,255.00
202699$2,361.0737$2,357.71
Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 55$2,400.0020$2,237.00
District 74$2,253.8620$3,727.09
District 14$2,000.2914$2,075.79
District 24$2,392.3713$2,255.00
Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: low bidder's median by quantity band
Quantity (AS)Low bidsLow-bid median
2 to 44$2,200.47
4 to 64$2,275.00
6 to 124$2,390.69
12 to 425$2,026.58
Midblock crosswalk: hybrid beacon assembly, & install complete assembly, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Midblock crosswalk: hybrid beacon assembly, & install complete assembly
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
26 AUG 2026T2A74District 212$2,423.67$2,151.003PREFERRED MATERIALS INC.FDOT
20 MAY 2026T7610District 74$3,728.00$3,727.596RUSSELL ENGINEERING, INC.FDOT
29 APR 2026T5881District 516$2,463.90$2,406.952MASCI GENERAL CONTRACTORS, INCFDOT
29 APR 2026T7562District 74$2,150.00$4,174.007WATSON CIVIL CONSTRUCTION, INC.FDOT
29 APR 2026T7615District 76$2,357.71$2,266.634PREFERRED MATERIALS INC.FDOT
25 MAR 2026T1925District 14$2,145.94$2,148.753AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
25 FEB 2026T1916District 16$1,928.08$1,928.085PREFERRED MATERIALS INC.FDOT
25 FEB 2026T2A36District 24$2,361.07$2,130.532CHINCHOR ELECTRIC INC.FDOT
28 JAN 2026T5874District 512$2,500.00$2,300.005MASCI GENERAL CONTRACTORS, INCFDOT
03 DEC 2025T2A48District 22$2,255.00$2,255.005COXWELL, J.B. CONTRACTING, INC.FDOT
24 SEP 2025T7567District 74$2,050.00$2,167.223SUPERIOR ASPHALT, INC.FDOT
11 JUN 2025T5851District 56$2,400.00$2,400.005JR. DAVIS CONSTRUCTION CO., INC.FDOT
28 MAY 2025T1900District 142$2,026.58$2,299.764TRAFFIC MANAGEMENT SOLUTIONS, LLCFDOT
28 MAY 2025T2991District 28$2,617.00$2,354.003AMERICAN LIGHTING AND SIGNALIZATION, LLC.FDOT
29 JAN 2025T5843District 512$2,154.26$2,154.265HUBBARD CONSTRUCTION COMPANYFDOT
Latest FDOT contracts carrying Midblock crosswalk: hybrid beacon assembly, & install complete assembly

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy