Mitered end section, optional - elliptical / arch, 18" cd unit price, Florida
Low bidders on FDOT contracts carried a median of $4,483.69 per EACH for item 0430-982625, mitered end section, optional - elliptical / arch, 18" cd, over the 24 months to 28 OCT 2026, across 9 low bids. Half of all 47 bids fell between $2,770.00 and $4,604.18.
- Owner
- Florida DOT
- Item
- 0430-982625
- Unit
- EACH
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $1,626.81 | 39 | $1,591.84 |
| 2019 | 9 | 9 | $1,774.50 | 43 | $1,700.00 |
| 2020 | 13 | 13 | $1,600.00 | 69 | $1,783.00 |
| 2021 | 10 | 10 | $1,922.01 | 46 | $2,064.17 |
| 2022 | 8 | 8 | $3,857.02 | 25 | $3,303.00 |
| 2023 | 7 | 7 | $3,302.04 | 26 | $3,266.02 |
| 2024 | 7 | 7 | $3,549.00 | 30 | $3,624.50 |
| 2025 | 3 | 3 | $4,500.00 | 15 | $4,400.00 |
| 2026 | 6 | 6 | $3,517.94 | 32 | $3,512.50 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T7591 | District 7 | 2 | $3,635.89 | $3,896.83 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 29 JUL 2026 | T4745 | District 4 | 1 | $5,544.12 | $5,111.24 | 6 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
| 10 JUN 2026 | T3952 | District 3 | 1 | $5,701.06 | $3,450.53 | 2 | RJ GORMAN CONTRACTING LLC | FDOT |
| 10 JUN 2026 | T5886 | District 5 | 2 | $2,800.00 | $3,500.00 | 7 | DB CIVIL CONSTRUCTION, LLC | FDOT |
| 20 MAY 2026 | T7595 | District 7 | 1 | $1,775.70 | $2,754.83 | 8 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 31 MAR 2026 | T3845 | District 3 | 3 | $3,400.00 | $2,907.07 | 4 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 29 OCT 2025 | T5869 | District 5 | 2 | $4,483.69 | $3,963.34 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 1 | $5,300.00 | $5,300.00 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 26 MAR 2025 | T5836 | District 5 | 7 | $4,500.00 | $4,400.00 | 7 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 24 | $3,900.00 | $3,256.05 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
| 12 JUN 2024 | T7532 | District 7 | 1 | $4,734.00 | $4,734.00 | 5 | ZEP CONSTRUCTION, INC. | FDOT |
| 22 MAY 2024 | T1865 | District 1 | 19 | $3,423.39 | $5,600.00 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 1 | $2,400.00 | $4,810.12 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
| 24 APR 2024 | T1894 | District 1 | 1 | $3,500.00 | $3,750.00 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 24 APR 2024 | T5824 | District 5 | 1 | $3,549.00 | $3,089.27 | 7 | MASCI GENERAL CONTRACTORS, INC | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.