Object marker, type 4 unit price, Florida
Low bidders on FDOT contracts carried a median of $300.00 per EACH for item 0705-10-4, object marker, type 4, over the 24 months to 28 OCT 2026, across 15 low bids. Half of all 78 bids fell between $218.76 and $348.75.
- Owner
- Florida DOT
- Item
- 0705-10-4
- Unit
- EACH
- Latest letting
- 26 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 5 | 5 | $175.00 | 24 | $180.00 |
| 2019 | 6 | 6 | $186.99 | 28 | $184.00 |
| 2020 | 4 | 4 | $172.00 | 13 | $175.00 |
| 2021 | 3 | 3 | $175.00 | 16 | $183.50 |
| 2022 | 8 | 8 | $231.00 | 29 | $225.00 |
| 2023 | 9 | 9 | $204.00 | 33 | $222.00 |
| 2024 | 6 | 6 | $367.01 | 20 | $321.31 |
| 2025 | 6 | 6 | $208.31 | 29 | $247.50 |
| 2026 | 6 | 6 | $305.00 | 41 | $301.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 3 | 3 | $247.50 |
| 3 to 3 | 4 | $339.51 |
| 3 to 3 | 4 | $335.00 |
| 3 to 26 | 4 | $259.18 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 AUG 2026 | T7605 | District 7 | 6 | $310.00 | $230.00 | 12 | LEON AMERICA CONSTRUCTION | FDOT |
| 10 JUN 2026 | T3952 | District 3 | 3 | $388.20 | $326.60 | 2 | RJ GORMAN CONTRACTING LLC | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 3 | $210.00 | $290.50 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 3 | $370.00 | $364.50 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 FEB 2026 | T7601 | District 7 | 3 | $218.35 | $231.38 | 6 | PREFERRED MATERIALS INC. | FDOT |
| 28 JAN 2026 | T2A54 | District 2 | 26 | $300.00 | $325.00 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 30 APR 2025 | T5850 | District 5 | 3 | $406.25 | $294.00 | 7 | V.A. PAVING, INC. | FDOT |
| 26 MAR 2025 | T7547 | District 7 | 3 | $300.00 | $250.00 | 3 | GOSALIA CONCRETE CONSTRUCTORS, INC. | FDOT |
| 26 MAR 2025 | T7569 | District 7 | 6 | $80.98 | $166.50 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 26 FEB 2025 | T7543 | District 7 | 3 | $162.75 | $166.38 | 4 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 26 FEB 2025 | T7565 | District 7 | 2 | $169.11 | $175.50 | 4 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 29 JAN 2025 | T6587 | District 6 | 2 | $247.50 | $300.00 | 7 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 30 OCT 2024 | T2999 | District 2 | 3 | $444.17 | $444.17 | 1 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 30 OCT 2024 | T3910 | District 3 | 3 | $379.03 | $350.00 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 30 OCT 2024 | T4690 | District 4 | 3 | $300.00 | $325.84 | 4 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.