Overhead static sign furnish & install, cantilever, 50 ft unit price, Florida
Low bidders on FDOT contracts carried a median of $143,750 per EACH for item 0700-4114, overhead static sign furnish & install, cantilever, 50 ft, over the 24 months to 28 OCT 2026, across 12 low bids. Half of all 61 bids fell between $117,000 and $190,000.
- Owner
- Florida DOT
- Item
- 0700-4114
- Unit
- EACH
- Latest letting
- 31 MAR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 13 | 13 | $81,000 | 65 | $85,000 |
| 2019 | 5 | 5 | $77,115 | 15 | $78,735 |
| 2020 | 6 | 6 | $71,138 | 32 | $73,688 |
| 2021 | 11 | 11 | $102,931 | 51 | $102,931 |
| 2022 | 9 | 10 | $130,978 | 42 | $137,475 |
| 2023 | 10 | 10 | $145,677 | 45 | $150,000 |
| 2024 | 4 | 4 | $128,500 | 17 | $131,000 |
| 2025 | 9 | 9 | $142,500 | 47 | $145,000 |
| 2026 | 3 | 3 | $168,864 | 14 | $148,690 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $135,055 |
| 1 to 2 | 3 | $142,500 |
| 2 to 3 | 3 | $165,000 |
| 3 to 6 | 3 | $117,800 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 31 MAR 2026 | T3845 | District 3 | 3 | $170,000 | $188,500 | 4 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 25 FEB 2026 | T4739 | District 4 | 2 | $168,864 | $157,567 | 5 | RANGER CONSTRUCTION INDUSTRIES, INC. | FDOT |
| 28 JAN 2026 | T2A56 | District 2 | 2 | $104,077 | $111,885 | 5 | DE MOYA CONTRACTING LLC | FDOT |
| 27 AUG 2025 | T4688 | District 4 | 1 | $327,845 | $280,000 | 7 | CENTRAL CIVIL CONSTRUCTION CO. | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 1 | $262,000 | $253,067 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 30 APR 2025 | T5793 | District 5 | 3 | $145,000 | $117,000 | 7 | P & S PAVING, INC. | FDOT |
| 26 MAR 2025 | T4710 | District 4 | 6 | $90,000 | $86,250 | 2 | OHLA USA INC | FDOT |
| 26 MAR 2025 | T4722 | District 4 | 1 | $142,500 | $145,252 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 3 | $165,000 | $150,000 | 5 | MASTEC CIVIL LLC | FDOT |
| 26 FEB 2025 | T4712 | District 4 | 1 | $113,246 | $113,246 | 5 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 3 | $117,800 | $130,000 | 5 | GLF POSILLICO JV | FDOT |
| 29 JAN 2025 | T6587 | District 6 | 1 | $135,055 | $132,599 | 7 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 19 JUN 2024 | T7501 | District 7 | 1 | $105,550 | $118,275 | 4 | WEBBER, LLC | FDOT |
| 22 MAY 2024 | T4655 | District 4 | 2 | $150,000 | $134,063 | 4 | OHLA USA INC | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 1 | $107,000 | $107,000 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.