Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, unit price, Florida

Low bidders on FDOT contracts carried a median of $1,254.90 per GM for item 0710-11133, painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, over the 24 months to 28 OCT 2026, across 39 low bids. Half of all 189 bids fell between $1,050.00 and $1,700.00.

Owner
Florida DOT
Item
0710-11133
Unit
GM
Latest letting
28 OCT 2026
$1,254.90Low bidder's median, per GM
$1,320.00Median of all bids, per GM
39Contracts in the window

By year of letting

Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201866$1,225.0026$1,175.00
201988$827.2531$1,107.51
202066$1,021.5523$935.29
20211413$705.5583$724.50
20221212$977.6236$1,127.33
20231818$1,332.2459$1,350.00
20241212$1,250.0041$1,250.00
20251818$1,256.3781$1,425.00
20261919$1,254.90100$1,248.20
Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 46$1,307.5044$1,310.00
District 29$1,432.0041$1,400.00
District 75$1,056.3130$1,106.51
District 16$1,143.8223$1,285.00
District 37$1,400.0022$1,492.50
District 54$1,160.5020$1,322.50
Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: low bidder's median by quantity band
Quantity (GM)Low bidsLow-bid median
0.02 to 0.069$1,391.00
0.06 to 0.1210$1,102.62
0.13 to 0.3210$1,416.00
0.34 to 2.3710$1,294.37
Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1937District 10.14$1,254.90$1,269.954AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T1949District 10.98$1,698.27$1,698.273OHLA USA INCFDOT
28 OCT 2026T2A73District 20.18$1,432.00$544.778C.W. ROBERTS CONTRACTING, INC.FDOT
28 OCT 2026T4765District 40.02$1,391.00$1,156.626GENERAL ASPHALT COMPANY, LLCFDOT
30 SEP 2026T3A26District 30.05$780.00$832.004C.W. ROBERTS CONTRACTING, INC.FDOT
30 SEP 2026T3A46District 30.07$1,050.00$1,200.003CAPITAL ASPHALT INCFDOT
26 AUG 2026T1945District 10.25$1,642.14$1,684.525PREFERRED MATERIALS INC.FDOT
26 AUG 2026T2A74District 20.02$1,400.00$1,400.003PREFERRED MATERIALS INC.FDOT
26 AUG 2026T4764District 40.13$1,889.76$1,600.009OHLA USA INCFDOT
20 MAY 2026T3987District 30.14$1,400.00$1,409.004C.W. ROBERTS CONTRACTING, INC.FDOT
20 MAY 2026T4666District 41.05$1,061.94$1,200.008OHLA USA INCFDOT
20 MAY 2026T7587District 70.16$1,056.31$1,130.005HUBBARD CONSTRUCTION COMPANYFDOT
20 MAY 2026T7595District 70.09$1,094.25$1,087.838C.W. ROBERTS CONTRACTING, INC.FDOT
29 APR 2026T7562District 70.10$960.00$1,000.007WATSON CIVIL CONSTRUCTION, INC.FDOT
25 MAR 2026T2963District 20.32$2,870.53$2,591.903HUBBARD CONSTRUCTION COMPANYFDOT
Latest FDOT contracts carrying Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide,

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy