Low bidders on FDOT contracts carried a median of $67.47 per SF for item 0548-12, retaining wall system, permanent, excluding barrier, over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 61 bids fell between $57.25 and $115.00.
- Owner
- Florida DOT
- Item
- 0548-12
- Unit
- SF
- Latest letting
- 29 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 12 | 13 | $37.00 | 63 | $32.17 |
| 2019 | 3 | 3 | $35.00 | 13 | $35.00 |
| 2020 | 6 | 6 | $48.83 | 31 | $51.15 |
| 2021 | 7 | 7 | $39.88 | 38 | $42.14 |
| 2022 | 5 | 5 | $45.00 | 23 | $49.31 |
| 2023 | 7 | 7 | $62.81 | 28 | $63.91 |
| 2024 | 5 | 5 | $80.46 | 21 | $83.25 |
| 2025 | 6 | 6 | $62.12 | 37 | $65.00 |
| 2026 | 4 | 4 | $84.97 | 24 | $105.65 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 JUL 2026 | T7619 | District 7 | 132 | $177.66 | $325.00 | 6 | TURTLE INFRASTRUCTURE PARTNERS, LLC | FDOT |
| 20 MAY 2026 | T4666 | District 4 | 56,048 | $52.00 | $48.50 | 8 | OHLA USA INC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 19,440 | $100.00 | $113.15 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T3951 | District 3 | 3,382 | $69.93 | $90.00 | 4 | RJ GORMAN CONTRACTING LLC | FDOT |
| 03 DEC 2025 | T4729 | District 4 | 79,332 | $59.25 | $72.27 | 8 | WEBBER, LLC | FDOT |
| 24 SEP 2025 | T2A24 | District 2 | 107,968 | $49.65 | $55.50 | 8 | MASTEC CIVIL LLC | FDOT |
| 30 APR 2025 | T4711 | District 4 | 9,629 | $118.00 | $116.50 | 4 | GLF CONSTRUCTION CORPORATION | FDOT |
| 30 APR 2025 | T5793 | District 5 | 79,240 | $48.00 | $53.00 | 7 | P & S PAVING, INC. | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 44,519 | $65.00 | $70.00 | 5 | MASTEC CIVIL LLC | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 18,054 | $239.50 | $120.00 | 5 | GLF POSILLICO JV | FDOT |
| 25 SEP 2024 | T2987 | District 2 | 148,349 | $44.00 | $65.00 | 4 | DE MOYA ASPHALT JOINT VENTURE | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 213,041 | $80.46 | $67.28 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
| 12 JUN 2024 | T7532 | District 7 | 5,972 | $110.00 | $96.00 | 5 | ZEP CONSTRUCTION, INC. | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 85,200 | $58.00 | $65.00 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
| 28 FEB 2024 | T7519 | District 7 | 4,560 | $97.00 | $90.22 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.