Sediment barrier unit price, Florida
Low bidders on FDOT contracts carried a median of $3.17 per LF for item 0104-10-3, sediment barrier, over the 24 months to 28 OCT 2026, across 320 low bids. Half of all 1,495 bids fell between $2.00 and $5.25.
- Owner
- Florida DOT
- Item
- 0104-10-3
- Unit
- LF
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 120 | 119 | $2.00 | 560 | $2.00 |
| 2019 | 142 | 139 | $2.00 | 628 | $2.00 |
| 2020 | 112 | 111 | $2.00 | 537 | $2.00 |
| 2021 | 146 | 141 | $2.00 | 625 | $2.00 |
| 2022 | 158 | 153 | $3.26 | 481 | $3.00 |
| 2023 | 172 | 169 | $3.88 | 534 | $3.54 |
| 2024 | 149 | 146 | $3.93 | 526 | $3.60 |
| 2025 | 150 | 151 | $3.24 | 678 | $3.34 |
| 2026 | 143 | 139 | $2.65 | 718 | $3.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 2 | 73 | $3.22 | 306 | $3.00 |
| District 3 | 76 | $4.50 | 269 | $5.00 |
| District 4 | 39 | $3.24 | 246 | $3.55 |
| District 7 | 41 | $2.32 | 229 | $3.00 |
| District 5 | 43 | $2.70 | 225 | $2.60 |
| District 1 | 39 | $2.23 | 177 | $2.50 |
| District 6 | 6 | $2.80 | 36 | $3.50 |
| StateWide | 3 | $7.75 | 7 | $6.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 18 to 728 | 80 | $5.76 |
| 732 to 2,286 | 80 | $3.50 |
| 2,287 to 7,733 | 80 | $2.76 |
| 7,892 to 141,575 | 80 | $2.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T1937 | District 1 | 56,291 | $0.90 | $1.07 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 28 OCT 2026 | T1941 | District 1 | 172 | $9.12 | $7.31 | 2 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 28 OCT 2026 | T1947 | District 1 | 11,663 | $1.05 | $1.32 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 28 OCT 2026 | T1949 | District 1 | 72,143 | n/a | $0.50 | 1 | OHLA USA INC | FDOT |
| 28 OCT 2026 | T2A73 | District 2 | 44,651 | $0.85 | $1.50 | 8 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 28 OCT 2026 | T2A82 | District 2 | 1,496 | $1.75 | $1.50 | 5 | WHITEHURST, V. E. & SONS, INC. | FDOT |
| 28 OCT 2026 | T2A84 | District 2 | 387 | $11.90 | $4.00 | 7 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 28 OCT 2026 | T2A86 | District 2 | 2,889 | $1.11 | $1.39 | 8 | PIGOTT ASPHALT AND SITEWORK LLC | FDOT |
| 28 OCT 2026 | T2A88 | District 2 | 4,558 | $1.50 | $1.96 | 6 | DB CIVIL CONSTRUCTION, LLC | FDOT |
| 28 OCT 2026 | T2B08 | District 2 | 228 | $14.93 | $14.93 | 1 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 28 OCT 2026 | T3970 | District 3 | 1,019 | $4.80 | $5.50 | 5 | RBM CONTRACTING SERVICES, LLC | FDOT |
| 28 OCT 2026 | T3A06 | District 3 | 95 | $10.00 | $11.04 | 2 | ACME BARRICADES LC | FDOT |
| 28 OCT 2026 | T3A21 | District 3 | 1,039 | $5.39 | $5.39 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 28 OCT 2026 | T3A25 | District 3 | 20,531 | $0.50 | $2.50 | 3 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 28 OCT 2026 | T5894 | District 5 | 48 | $10.00 | $12.00 | 5 | AUM CONSTRUCTION INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way