Shoulder concrete barrier, curb and gutter barrier unit price, Florida

Low bidders on FDOT contracts carried a median of $371.00 per LF for item 0521-72-43, shoulder concrete barrier, curb and gutter barrier, over the 24 months to 28 OCT 2026, across 14 low bids. Half of all 68 bids fell between $339.29 and $563.51.

Owner
Florida DOT
Item
0521-72-43
Unit
LF
Latest letting
29 JUL 2026
$371.00Low bidder's median, per LF
$420.00Median of all bids, per LF
14Contracts in the window

By year of letting

Shoulder concrete barrier, curb and gutter barrier, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201966$208.9826$223.00
202044$527.5019$421.56
202188$373.0036$373.00
202244$331.5217$248.00
202344$394.0013$463.00
202477$329.6031$376.00
202577$365.0027$375.00
202677$420.0041$471.00
Shoulder concrete barrier, curb and gutter barrier, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Shoulder concrete barrier, curb and gutter barrier, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 63$420.0023$488.38
District 14$408.5017$501.60
District 43$252.2413$323.00
District 33$420.0010$455.50
Shoulder concrete barrier, curb and gutter barrier, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Shoulder concrete barrier, curb and gutter barrier, FDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
23 to 403$420.00
45 to 734$470.00
80 to 1993$330.00
615 to 7934$265.74
Shoulder concrete barrier, curb and gutter barrier, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Shoulder concrete barrier, curb and gutter barrier
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
29 JUL 2026T1939District 173$800.00$680.674OHLA USA INCFDOT
29 JUL 2026T6595District 638$420.00$578.2712BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&EFDOT
31 MAR 2026T3845District 340$280.00$383.254PHOENIX CONSTRUCTION SERVICES, INC.FDOT
25 MAR 2026T1920District 159$440.00$508.156SEMA CONSTRUCTION, INC.FDOT
25 MAR 2026T3A09District 345$420.00$500.003CAPITAL ASPHALT INCFDOT
25 MAR 2026T6591District 6141$330.00$337.167WEEKLEY ASPHALT PAVING, INC.FDOT
28 JAN 2026T5874District 5615$279.23$380.005MASCI GENERAL CONTRACTORS, INCFDOT
11 JUN 2025T1904District 180$377.00$439.302RUSSELL ENGINEERING, INC.FDOT
28 MAY 2025T1926District 1199$320.00$348.015WATSON CIVIL CONSTRUCTION, INC.FDOT
30 APR 2025T6603District 623$885.00$700.004GENERAL ASPHALT COMPANY, LLCFDOT
26 MAR 2025T4699District 4696$252.24$375.004TIMOTHY ROSE CONTRACTING, INC.FDOT
26 FEB 2025T3853District 355$500.00$500.003COLLINS LAND SERVICES, LLCFDOT
26 FEB 2025T4691District 4793$365.00$250.005MASTEC CIVIL LLCFDOT
26 FEB 2025T4697District 4661$215.00$331.504OHLA USA INCFDOT
25 SEP 2024T2987District 2134$375.00$398.004DE MOYA ASPHALT JOINT VENTUREFDOT
Latest FDOT contracts carrying Shoulder concrete barrier, curb and gutter barrier

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.