Sign panel, furnish & install overhead mount, 31-50 sf unit price, Florida
Low bidders on FDOT contracts carried a median of $3,069.23 per EACH for item 0700-3204, sign panel, furnish & install overhead mount, 31-50 sf, over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 43 bids fell between $2,375.02 and $3,496.93.
- Owner
- Florida DOT
- Item
- 0700-3204
- Unit
- EACH
- Latest letting
- 30 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 7 | 7 | $1,800.00 | 26 | $1,816.50 |
| 2019 | 4 | 4 | $1,926.51 | 15 | $2,120.00 |
| 2021 | 5 | 5 | $1,690.00 | 25 | $1,690.00 |
| 2022 | 13 | 13 | $2,482.79 | 50 | $2,348.13 |
| 2023 | 8 | 8 | $2,239.00 | 27 | $2,560.00 |
| 2024 | 5 | 5 | $2,500.00 | 22 | $2,421.49 |
| 2025 | 7 | 7 | $3,000.00 | 29 | $3,300.00 |
| 2026 | 3 | 3 | $3,138.47 | 14 | $3,036.50 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 SEP 2026 | T3A23 | District 3 | 2 | $3,300.00 | $558.35 | 3 | AMERICAN SAND & X-CAVATION, INC. DBA AMERICAN SAND & ASPHALT PAVING | FDOT |
| 29 JUL 2026 | T5891 | District 5 | 2 | $2,415.00 | $2,375.02 | 4 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 20 MAY 2026 | T4737 | District 4 | 2 | $3,138.47 | $3,262.50 | 7 | TRAFFIC MANAGEMENT SOLUTIONS, LLC | FDOT |
| 29 OCT 2025 | T2A34 | District 2 | 2 | $3,535.87 | $2,767.93 | 2 | ANDERSON COLUMBIA CO., INC. | FDOT |
| 27 AUG 2025 | T4702 | District 4 | 4 | $3,384.21 | $3,365.86 | 8 | THE STOUT GROUP LLC | FDOT |
| 30 JUL 2025 | T3973 | District 3 | 1 | $2,700.00 | $2,752.37 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 30 APR 2025 | T5793 | District 5 | 5 | $1,950.00 | $4,800.00 | 7 | P & S PAVING, INC. | FDOT |
| 26 MAR 2025 | T4710 | District 4 | 1 | $3,000.00 | $4,195.00 | 2 | OHLA USA INC | FDOT |
| 26 MAR 2025 | T7547 | District 7 | 1 | $3,300.00 | $3,300.00 | 3 | GOSALIA CONCRETE CONSTRUCTORS, INC. | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 1 | $1,616.00 | $1,750.00 | 5 | GLF POSILLICO JV | FDOT |
| 28 AUG 2024 | T4682 | District 4 | 28 | $1,400.00 | $1,485.00 | 7 | OHLA USA INC | FDOT |
| 22 MAY 2024 | T4655 | District 4 | 1 | $2,500.00 | $3,200.00 | 4 | OHLA USA INC | FDOT |
| 22 MAY 2024 | T6566 | District 6 | 1 | $3,000.00 | $2,750.00 | 6 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A B | FDOT |
| 22 MAY 2024 | T7540 | District 7 | 1 | $2,427.98 | $2,427.98 | 3 | PREFERRED MATERIALS INC. | FDOT |
| 31 JAN 2024 | T3892-R0 | District 3 | 6 | $4,536.29 | $4,018.14 | 2 | ANDERSON COLUMBIA CO., INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.