Steel mast arm assembly, and install, single arm 30' unit price, Florida
Low bidders on FDOT contracts carried a median of $57,302 per EACH for item 0649-21-1, steel mast arm assembly, and install, single arm 30', over the 24 months to 28 OCT 2026, across 19 low bids. Half of all 91 bids fell between $51,929 and $64,306.
- Owner
- Florida DOT
- Item
- 0649-21-1
- Unit
- EACH
- Latest letting
- 10 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 11 | 11 | $25,857 | 51 | $28,431 |
| 2019 | 11 | 11 | $32,885 | 45 | $32,706 |
| 2020 | 3 | 3 | $40,053 | 8 | $49,427 |
| 2021 | 9 | 9 | $40,000 | 42 | $37,266 |
| 2022 | 9 | 9 | $50,000 | 30 | $50,050 |
| 2023 | 8 | 8 | $77,450 | 25 | $75,500 |
| 2024 | 9 | 9 | $60,246 | 33 | $66,450 |
| 2025 | 9 | 9 | $55,000 | 42 | $57,850 |
| 2026 | 7 | 7 | $62,305 | 39 | $54,000 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 5 | $55,774 | 27 | $57,302 |
| District 6 | 3 | $54,248 | 18 | $54,252 |
| District 1 | 4 | $70,025 | 15 | $62,532 |
| District 2 | 3 | $81,200 | 12 | $65,595 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 4 | $57,887 |
| 1 to 1 | 5 | $57,302 |
| 1 to 2 | 5 | $52,000 |
| 2 to 10 | 5 | $62,305 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 10 JUN 2026 | T7534 | District 7 | 7 | $62,305 | $72,377 | 4 | PREFERRED MATERIALS INC. | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 1 | $57,302 | $48,636 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 20 MAY 2026 | T7610 | District 7 | 10 | $52,400 | $53,200 | 6 | RUSSELL ENGINEERING, INC. | FDOT |
| 25 MAR 2026 | T6589 | District 6 | 1 | $52,000 | $52,019 | 6 | AUM CONSTRUCTION INC. | FDOT |
| 25 FEB 2026 | T1813 | District 1 | 1 | $66,500 | $58,489 | 4 | SUPERIOR ASPHALT, INC. | FDOT |
| 25 FEB 2026 | T1916 | District 1 | 2 | $62,532 | $62,532 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 28 JAN 2026 | T1922 | District 1 | 2 | $73,550 | $52,429 | 4 | SUPERIOR ASPHALT, INC. | FDOT |
| 03 DEC 2025 | T2A48 | District 2 | 1 | $81,200 | $61,000 | 5 | COXWELL, J.B. CONTRACTING, INC. | FDOT |
| 29 OCT 2025 | T6621 | District 6 | 1 | $54,248 | $54,624 | 6 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
| 27 AUG 2025 | T5872 | District 5 | 3 | $63,363 | $61,568 | 4 | BLACKTIP SERVICES INCORPORATED | FDOT |
| 11 JUN 2025 | T1904 | District 1 | 1 | $75,236 | $84,643 | 2 | RUSSELL ENGINEERING, INC. | FDOT |
| 11 JUN 2025 | T5851 | District 5 | 1 | $54,000 | $59,562 | 5 | JR. DAVIS CONSTRUCTION CO., INC. | FDOT |
| 28 MAY 2025 | T4575 | District 4 | 2 | $51,457 | $55,229 | 4 | ROADWAY CONSTRUCTION, LLC | FDOT |
| 26 FEB 2025 | T4691 | District 4 | 1 | $55,000 | $52,900 | 5 | MASTEC CIVIL LLC | FDOT |
| 26 FEB 2025 | T6588 | District 6 | 3 | $55,000 | $54,628 | 6 | AUM CONSTRUCTION INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.