Thermoplastic, standard, solid, 8" for interchange and urban island unit price, Florida

Low bidders on FDOT contracts carried a median of $7,538.76 per GM for item 0711-11102, thermoplastic, standard, solid, 8" for interchange and urban island, over the 24 months to 28 OCT 2026, across 82 low bids. Half of all 404 bids fell between $6,509.90 and $10,000.

Owner
Florida DOT
Item
0711-11102
Unit
GM
Latest letting
28 OCT 2026
$7,538.76Low bidder's median, per GM
$7,742.80Median of all bids, per GM
82Contracts in the window

By year of letting

Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20181313$6,273.4154$5,529.64
20191616$5,968.7972$5,712.25
20202424$5,771.82138$5,500.00
20213232$5,614.24146$5,526.98
20223333$6,825.00116$7,050.00
20233434$7,985.6499$7,975.52
20244040$8,350.00141$8,500.00
20253636$9,450.00163$8,800.00
20263636$6,946.93206$7,342.32
Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 518$9,782.5094$9,502.50
District 220$12,32484$9,025.00
District 415$6,666.0083$7,725.00
District 610$6,946.9364$7,000.00
District 77$6,417.5739$6,716.64
District 38$9,300.0023$10,500
District 14$7,170.3517$7,962.37
Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: low bidder's median by quantity band
Quantity (GM)Low bidsLow-bid median
0.00 to 0.0520$8,090.00
0.05 to 0.1221$7,167.43
0.12 to 0.2820$7,320.00
0.31 to 1.4021$8,207.30
Thermoplastic, standard, solid, 8" for interchange and urban island, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Thermoplastic, standard, solid, 8" for interchange and urban island
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1947District 10.04$7,173.27$6,836.644AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T2A84District 20.05$5,452.66$5,600.007ANDERSON COLUMBIA CO., INC.FDOT
28 OCT 2026T5894District 50.02$25,000$12,1185AUM CONSTRUCTION INC.FDOT
30 SEP 2026T3A26District 30.08$5,600.00$5,720.004C.W. ROBERTS CONTRACTING, INC.FDOT
30 SEP 2026T5893District 50.12$7,560.00$6,780.008MASCI GENERAL CONTRACTORS, INCFDOT
30 SEP 2026T6593District 60.23$6,893.87$6,893.875OHLA USA INCFDOT
26 AUG 2026T2A74District 20.07$5,500.00$8,200.003PREFERRED MATERIALS INC.FDOT
26 AUG 2026T3998District 30.06$8,409.99$8,409.993ANDERSON COLUMBIA CO., INC.FDOT
26 AUG 2026T4764District 40.03$7,258.06$8,066.729OHLA USA INCFDOT
29 JUL 2026T4745District 40.09$6,649.18$7,250.006FLORIDA ENGINEERING & DEVELOPMENT CORPFDOT
29 JUL 2026T5891District 51.18$9,975.00$8,405.294MASCI GENERAL CONTRACTORS, INCFDOT
29 JUL 2026T6595District 60.14$6,700.00$6,489.7012BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A BC&EFDOT
29 JUL 2026T6625District 60.01$6,500.00$7,227.517FLORIDA SIGNAL & LIGHTING CONTRACTORS, INC.FDOT
29 JUL 2026T7599District 70.75$5,793.00$6,352.494C.W. ROBERTS CONTRACTING, INC.FDOT
15 JUN 2026T5885District 50.32$9,765.00$9,837.504C.W. ROBERTS CONTRACTING, INC.FDOT
Latest FDOT contracts carrying Thermoplastic, standard, solid, 8" for interchange and urban island

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy