Tree removal unit price, Florida

Low bidders on FDOT contracts carried a median of $1,566.26 per EACH for item 0110-23, tree removal, over the 24 months to 28 OCT 2026, across 26 low bids. Half of all 143 bids fell between $1,200.00 and $2,915.00.

Owner
Florida DOT
Item
0110-23
Unit
EACH
Latest letting
28 OCT 2026
$1,566.26Low bidder's median, per EACH
$1,750.00Median of all bids, per EACH
26Contracts in the window

By year of letting

Tree removal, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202011$5,000.006$2,500.00
2021108$627.1074$636.00
20221312$855.1072$1,000.00
20231010$1,079.9137$1,150.00
20241313$2,750.0049$2,100.00
20251313$1,512.5063$1,770.00
20261010$1,440.0571$1,647.61
Tree removal, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Tree removal, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 49$1,512.5049$1,575.00
District 76$1,368.2437$1,730.80
District 64$2,100.0026$2,178.93
District 14$2,225.0017$1,500.00
Tree removal, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Tree removal, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 16$3,375.00
1 to 37$1,500.00
3 to 56$1,950.00
7 to 1407$1,503.97
Tree removal, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Tree removal
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T2A88District 21$8,491.30$1,750.006DB CIVIL CONSTRUCTION, LLCFDOT
28 OCT 2026T4765District 44$3,300.00$1,800.006GENERAL ASPHALT COMPANY, LLCFDOT
26 AUG 2026T1948District 14$270.00$1,500.0010LEON AMERICA CONSTRUCTIONFDOT
26 AUG 2026T2A75District 21$3,750.00$4,689.315PREFERRED MATERIALS INC.FDOT
26 AUG 2026T7604District 75$500.00$1,500.009LEON AMERICA CONSTRUCTIONFDOT
29 JUL 2026T7619District 71$1,232.50$1,810.396TURTLE INFRASTRUCTURE PARTNERS, LLCFDOT
29 APR 2026T7611District 746$1,647.61$1,974.329PREFERRED MATERIALS INC.FDOT
25 MAR 2026T4740District 43$2,700.00$926.229GENERAL ASPHALT COMPANY, LLCFDOT
25 MAR 2026T6589District 612$1,200.00$1,773.006AUM CONSTRUCTION INC.FDOT
28 JAN 2026T6618District 61$900.00$920.005WEEKLEY ASPHALT PAVING, INC.FDOT
24 SEP 2025T7566District 71$500.00$775.006BURGESS CIVIL, LLCFDOT
27 AUG 2025T4688District 42$1,620.03$1,620.037CENTRAL CIVIL CONSTRUCTION CO.FDOT
30 JUL 2025T4726District 423$1,100.00$2,025.006PEDRAIL SYSTEMS LLCFDOT
28 MAY 2025T4724District 42$1,287.50$1,770.005FLORIDA ENGINEERING & DEVELOPMENT CORPFDOT
28 MAY 2025T7533District 73$5,000.00$6,400.003DB CIVIL CONSTRUCTION, LLCFDOT
Latest FDOT contracts carrying Tree removal

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy