Utility pipe,remove & dispose, 5- 7.9" unit price, Florida

Low bidders on FDOT contracts carried a median of $37.50 per LF for item 1050-16003, utility pipe,remove & dispose, 5- 7.9", over the 24 months to 28 OCT 2026, across 12 low bids. Half of all 58 bids fell between $26.72 and $75.41.

Owner
Florida DOT
Item
1050-16003
Unit
LF
Latest letting
30 SEP 2026
$37.50Low bidder's median, per LF
$42.38Median of all bids, per LF
12Contracts in the window

By year of letting

Utility pipe,remove & dispose, 5- 7.9", FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201888$26.0038$19.90
201955$11.1226$15.25
202066$20.6532$18.69
202155$23.0030$25.50
202255$22.0016$19.80
202355$47.0017$47.00
202455$50.0021$55.00
202522$63.366$21.50
20261010$37.5052$48.38
Utility pipe,remove & dispose, 5- 7.9", FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Utility pipe,remove & dispose, 5- 7.9", FDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
10 to 603$80.68
90 to 3003$100.29
390 to 7923$26.00
1,170 to 2,6373$42.00
Utility pipe,remove & dispose, 5- 7.9", FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Utility pipe,remove & dispose, 5- 7.9"
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
30 SEP 2026T6398District 61,170$65.00$64.124OHLA USA INCFDOT
10 JUN 2026T7534District 7300$100.29$81.384PREFERRED MATERIALS INC.FDOT
20 MAY 2026T4666District 410$101.52$85.258OHLA USA INCFDOT
20 MAY 2026T5882District 5122$4.00$26.0010MASCI GENERAL CONTRACTORS, INCFDOT
20 MAY 2026T7576District 723$80.68$80.683C.W. ROBERTS CONTRACTING, INC.FDOT
29 APR 2026T5881District 5390$11.50$40.752MASCI GENERAL CONTRACTORS, INCFDOT
29 APR 2026T7562District 72,637$42.00$35.007WATSON CIVIL CONSTRUCTION, INC.FDOT
31 MAR 2026T3845District 3540$26.00$19.504PHOENIX CONSTRUCTION SERVICES, INC.FDOT
25 MAR 2026T1920District 1792$33.00$37.506SEMA CONSTRUCTION, INC.FDOT
28 JAN 2026T7580District 760$30.80$40.404AJ GENERAL CONSTRUCTION SERVICES, INC.FDOT
28 MAY 2025T4575District 41,183$11.73$15.874ROADWAY CONSTRUCTION, LLCFDOT
29 JAN 2025T7502District 790$115.00$78.882WATSON CIVIL CONSTRUCTION, INC.FDOT
14 AUG 2024T1899District 114,982$32.50$45.474LANE CONSTRUCTION CORPORATION (THE)FDOT
12 JUN 2024T1875District 16,651$70.98$55.003HUBBARD CONSTRUCTION COMPANYFDOT
12 JUN 2024T7532District 7965$50.00$63.005ZEP CONSTRUCTION, INC.FDOT
Latest FDOT contracts carrying Utility pipe,remove & dispose, 5- 7.9"

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.