Agg ditch checks unit price, Illinois
Low bidders on IDOT contracts carried a median of $118.50 per TON for item 28000315, agg ditch checks, over the 24 months to 18 SEP 2026, across 8 low bids. Half of all 28 bids fell between $100.00 and $250.00.
- Owner
- Illinois DOT
- Item
- 28000315
- Unit
- TON
- Latest letting
- 12 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 7 | 7 | $60.00 | 34 | $75.75 |
| 2022 | 7 | 7 | $90.00 | 15 | $119.80 |
| 2023 | 15 | 15 | $105.00 | 52 | $139.50 |
| 2024 | 9 | 9 | $102.96 | 32 | $101.48 |
| 2025 | 3 | 3 | $50.00 | 9 | $150.00 |
| 2026 | 5 | 5 | $120.00 | 19 | $220.00 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 JUN 2026 | 62L30 | District 01 | 3 | $220.00 | $220.00 | 6 | D. Construction, Inc. | IDOT |
| 12 JUN 2026 | 62V08 | District 01 | 66 | $60.00 | $86.42 | 3 | D. Construction, Inc. | IDOT |
| 27 FEB 2026 | 62P01 | District 01 | 9 | $250.00 | $250.00 | 4 | Austin Tyler Construction, Inc. | IDOT |
| 27 FEB 2026 | 64R72 | District 02 | 102 | $120.00 | $320.86 | 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | IDOT |
| 27 FEB 2026 | 93845 | District 06 | 10 | $117.00 | $108.50 | 4 | Laverdiere Construction, Inc. | IDOT |
| 01 AUG 2025 | 64C24 | District 02 | 151 | $49.09 | $153.50 | 5 | OHLA Central, Inc. | IDOT |
| 13 JUN 2025 | 93836 | District 06 | 50 | $50.00 | $99.00 | 3 | County Contractors, Inc. | IDOT |
| 25 APR 2025 | 68A65 | District 04 | 24 | $240.35 | $240.35 | 1 | R. A. Cullinan and Son, a div of UCM, Inc. | IDOT |
| 02 AUG 2024 | 61J93 | District 01 | 210 | $210.00 | $100.00 | 5 | Plote Construction Inc. and Dunnet Bay Construction Company JV | IDOT |
| 02 AUG 2024 | 66K82 | District 03 | 607 | $90.00 | $90.00 | 1 | Advanced Asphalt Company | IDOT |
| 14 JUN 2024 | 60J10 | District 01 | 38.50 | $102.96 | $102.96 | 3 | IHC Construction Companies, L.L.C. | IDOT |
| 26 APR 2024 | 60P75 | District 01 | 1,110.60 | $60.01 | $65.00 | 6 | R. W. Dunteman Company | IDOT |
| 26 APR 2024 | 61K35 | District 01 | 76 | $115.00 | $102.97 | 4 | Curran Contracting Company | IDOT |
| 26 APR 2024 | 68880 | District 04 | 256 | $75.00 | $89.00 | 2 | Stark Excavating, Inc. | IDOT |
| 19 JAN 2024 | 61J67 | District 01 | 6 | $144.31 | $200.00 | 3 | Herlihy Mid-Continent Company | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.