Aggregate-temp access unit price, Illinois
Low bidders on IDOT contracts carried a median of $48.00 per TON for item 40201000, aggregate-temp access, over the 24 months to 18 SEP 2026, across 82 low bids. Half of all 276 bids fell between $35.00 and $72.39.
- Owner
- Illinois DOT
- Item
- 40201000
- Unit
- TON
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 38 | 33 | $30.00 | 137 | $31.00 |
| 2022 | 44 | 43 | $43.00 | 150 | $35.00 |
| 2023 | 53 | 50 | $47.00 | 152 | $45.00 |
| 2024 | 50 | 48 | $42.00 | 153 | $44.50 |
| 2025 | 48 | 42 | $50.00 | 149 | $50.00 |
| 2026 | 28 | 28 | $45.00 | 94 | $50.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 01 | 17 | $35.50 | 85 | $40.00 |
| District 08 | 27 | $45.25 | 80 | $54.75 |
| District 02 | 10 | $34.50 | 38 | $39.50 |
| District 06 | 7 | $60.00 | 18 | $63.50 |
| District 09 | 6 | $51.49 | 17 | $53.00 |
| District 03 | 8 | $46.50 | 16 | $49.00 |
| District 04 | 3 | $35.00 | 11 | $55.96 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 5 to 50 | 20 | $48.00 |
| 50 to 100 | 21 | $51.00 |
| 100 to 240 | 20 | $51.27 |
| 250 to 3,524 | 21 | $37.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 97892 | District 08 | 76 | $51.00 | $51.00 | 3 | Plocher Construction Company, Inc. | IDOT |
| 18 SEP 2026 | 97894 | District 08 | 100 | $42.00 | $60.00 | 5 | Hank's Excavating & Landscaping, Inc. | IDOT |
| 31 JUL 2026 | 78520 | District 09 | 50 | $96.06 | $74.53 | 2 | E. T. Simonds Construction Company | IDOT |
| 31 JUL 2026 | 85781 | District 02 | 306 | $32.00 | $34.48 | 4 | Miller Trucking & Excavating Company | IDOT |
| 31 JUL 2026 | 97866 | District 08 | 750 | $43.50 | $41.75 | 4 | Mayer Landscaping, Inc. | IDOT |
| 12 JUN 2026 | 64L94 | District 02 | 788 | $60.00 | $55.00 | 4 | Valley Construction Co. | IDOT |
| 12 JUN 2026 | 97896 | District 08 | 15 | $40.00 | $86.10 | 3 | Stutz Excavating, Inc. | IDOT |
| 24 APR 2026 | 61M17 | District 01 | 200 | $35.50 | $28.00 | 5 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 24 APR 2026 | 61M37 | District 01 | 72 | $45.00 | $36.75 | 4 | R. W. Dunteman Company | IDOT |
| 24 APR 2026 | 72503 | District 06 | 93 | $60.00 | $60.00 | 3 | Phoenix Corporation of the Quad Cities | IDOT |
| 24 APR 2026 | 93783 | District 06 | 35 | $75.00 | $75.00 | 1 | K. E. Vas Company | IDOT |
| 24 APR 2026 | 97840 | District 08 | 100 | $77.00 | $77.00 | 2 | Christ Bros. Asphalt, Inc. | IDOT |
| 27 FEB 2026 | 76B42 | District 08 | 50 | $43.00 | $43.00 | 3 | C-Hill Civil Contractors, Inc. | IDOT |
| 27 FEB 2026 | 97872 | District 08 | 639 | $37.00 | $41.00 | 2 | DMS Contracting, Inc. | IDOT |
| 27 FEB 2026 | 97882 | District 08 | 100 | $35.00 | $50.00 | 2 | Stutz Excavating, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.