Bkwy dev cou ss scrn unit price, Illinois
Low bidders on IDOT contracts carried a median of $250.00 per EACH for item 83800650, bkwy dev cou ss scrn, over the 24 months to 18 SEP 2026, across 50 low bids. Half of all 124 bids fell between $207.98 and $442.50.
- Owner
- Illinois DOT
- Item
- 83800650
- Unit
- EACH
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 12 | 12 | $147.02 | 32 | $147.19 |
| 2022 | 14 | 14 | $170.00 | 26 | $170.78 |
| 2023 | 17 | 17 | $260.00 | 39 | $260.00 |
| 2024 | 18 | 18 | $246.09 | 36 | $221.52 |
| 2025 | 25 | 25 | $271.70 | 62 | $261.84 |
| 2026 | 18 | 18 | $237.78 | 48 | $260.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 09 | 10 | $228.00 | 27 | $250.00 |
| District 01 | 4 | $422.34 | 19 | $581.00 |
| District 06 | 9 | $214.37 | 19 | $217.35 |
| District 07 | 7 | $250.00 | 17 | $269.97 |
| District 03 | 7 | $440.00 | 11 | $538.19 |
| District 05 | 3 | $191.00 | 10 | $195.50 |
| District 04 | 4 | $293.39 | 10 | $281.62 |
| District 02 | 5 | $247.31 | 8 | $248.76 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 3 to 12 | 12 | $269.24 |
| 15 to 52 | 13 | $320.00 |
| 56 to 84 | 12 | $224.16 |
| 84 to 724 | 13 | $214.37 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 64V85 | District 02 | 84 | $366.80 | $366.80 | 1 | Helm Electric Facility Solutions, Inc. d/b/a Helm Electric | IDOT |
| 18 SEP 2026 | 64V86 | District 02 | 84 | $210.00 | $210.00 | 1 | Davenport Electric Contract Company | IDOT |
| 18 SEP 2026 | 74D06 | District 07 | 64 | $250.00 | $259.99 | 2 | Samron Midwest Contracting, Inc. | IDOT |
| 31 JUL 2026 | 92621 | District 06 | 228 | $223.38 | $313.75 | 4 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 12 JUN 2026 | 62U72 | District 01 | 256 | $181.70 | $180.88 | 5 | Martam Construction Incorporated | IDOT |
| 12 JUN 2026 | 72509 | District 06 | 88 | $214.37 | $215.19 | 2 | Bodine Electric of Decatur | IDOT |
| 12 JUN 2026 | 76M95 | District 08 | 15 | $655.00 | $650.00 | 3 | Samron Midwest Contracting, Inc. | IDOT |
| 24 APR 2026 | 66M55 | District 03 | 20 | $440.00 | $440.00 | 1 | D. Construction, Inc. | IDOT |
| 24 APR 2026 | 66T25 | District 03 | 92 | $225.56 | $544.37 | 4 | Helm Electric Facility Solutions, Inc. d/b/a Helm Electric | IDOT |
| 24 APR 2026 | 72N43 | District 06 | 3 | $525.00 | $525.00 | 3 | Baxmeyer Construction, Inc. | IDOT |
| 24 APR 2026 | 74E31 | District 07 | 10 | $190.00 | $190.00 | 1 | Bodine Electric of Decatur | IDOT |
| 27 FEB 2026 | 68J46 | District 04 | 4 | $266.78 | $281.62 | 4 | Otto Baum Company, Inc. | IDOT |
| 27 FEB 2026 | 68K06 | District 04 | 52 | $320.00 | $272.50 | 2 | Laser Electric, Inc. | IDOT |
| 27 FEB 2026 | 99757 | District 09 | 16 | $260.00 | $260.00 | 3 | Samron Midwest Contracting, Inc. | IDOT |
| 16 JAN 2026 | 72G90 | District 06 | 8 | $170.92 | $170.92 | 1 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.