Low bidders on IDOT contracts carried a median of $23,648 per EACH for item 54001002, box cul end sec c2, over the 24 months to 18 SEP 2026, across 13 low bids. Half of all 37 bids fell between $14,000 and $28,550.
- Owner
- Illinois DOT
- Item
- 54001002
- Unit
- EACH
- Latest letting
- 12 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 11 | 11 | $10,850 | 27 | $12,800 |
| 2022 | 9 | 9 | $15,800 | 27 | $15,908 |
| 2023 | 16 | 16 | $20,000 | 43 | $21,000 |
| 2024 | 13 | 13 | $25,000 | 32 | $21,450 |
| 2025 | 4 | 4 | $35,525 | 9 | $24,319 |
| 2026 | 7 | 7 | $23,750 | 22 | $21,865 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 08 | 3 | $23,750 | 10 | $21,865 |
| District 09 | 4 | $18,752 | 10 | $23,064 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $23,648 |
| 2 to 2 | 3 | $15,505 |
| 2 to 2 | 3 | $23,750 |
| 2 to 3 | 4 | $25,125 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 JUN 2026 | 62U72 | District 01 | 1 | $23,648 | $15,200 | 5 | Martam Construction Incorporated | IDOT |
| 12 JUN 2026 | 66M92 | District 03 | 2 | $12,975 | $17,800 | 5 | Iroquois Paving Corporation | IDOT |
| 24 APR 2026 | 61L48 | District 01 | 2 | $77,266 | $53,569 | 2 | William Charles Construction Company, LLC | IDOT |
| 27 FEB 2026 | 64R72 | District 02 | 1 | $30,000 | $27,125 | 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | IDOT |
| 27 FEB 2026 | 76B42 | District 08 | 2 | $23,750 | $23,750 | 3 | C-Hill Civil Contractors, Inc. | IDOT |
| 27 FEB 2026 | 97872 | District 08 | 3 | $36,250 | $28,000 | 3 | DMS Contracting, Inc. | IDOT |
| 16 JAN 2026 | 64L27 | District 02 | 1 | $8,000.00 | $10,250 | 2 | Martin & Company Excavating | IDOT |
| 07 NOV 2025 | 68B60 | District 04 | 2 | $67,961 | $67,961 | 1 | Gunther Construction, a div of UCM, Inc. | IDOT |
| 07 NOV 2025 | 78813 | District 09 | 2 | $14,000 | $22,388 | 3 | Samron Midwest Contracting, Inc. | IDOT |
| 13 JUN 2025 | 78399 | District 09 | 2 | $22,000 | $22,870 | 2 | Samron Midwest Contracting, Inc. | IDOT |
| 07 MAR 2025 | 78844 | District 09 | 2 | $49,050 | $49,050 | 3 | Sierra Bravo Contractors, LLC | IDOT |
| 13 DEC 2024 | 78633 | District 09 | 2 | $15,505 | $16,027 | 2 | E. T. Simonds Construction Company | IDOT |
| 08 NOV 2024 | 97372 | District 08 | 2 | $10,175 | $9,837.50 | 4 | DMS Contracting, Inc. | IDOT |
| 14 JUN 2024 | 70C14 | District 05 | 2 | $27,260 | $22,308 | 2 | Howell Paving, Inc. | IDOT |
| 14 JUN 2024 | 87801 | District 03 | 2 | $6,000.00 | $7,250.00 | 2 | Advanced Asphalt Company | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.