Low bidders on IDOT contracts carried a median of $62.00 per SY for item Z0012130, br deck scar 3/4, over the 24 months to 18 SEP 2026, across 59 low bids. Half of all 203 bids fell between $60.00 and $114.98.

Owner
Illinois DOT
Item
Z0012130
Unit
SY
Latest letting
31 JUL 2026
$62.00Low bidder's median, per SY
$78.23Median of all bids, per SY
59Contracts in the window

By year of letting

Br deck scar 3/4, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20214747$49.60227$57.50
20224141$70.43130$72.00
20235050$68.50160$77.33
20246666$60.00215$75.00
20253232$61.84102$70.00
202688$61.0030$93.00
Br deck scar 3/4, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Br deck scar 3/4, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0121$56.00111$75.23
District 0712$106.7532$101.00
District 026$85.0016$91.50
District 057$58.2216$64.00
District 065$61.1312$73.13
District 034$60.007$68.00
District 043$78.237$84.00
Br deck scar 3/4, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Br deck scar 3/4, IDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
162 to 65614$89.00
716 to 1,11515$68.00
1,128 to 1,80815$60.00
2,149 to 36,83715$51.46
Br deck scar 3/4, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Br deck scar 3/4
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202662Y20District 011,128$54.00$96.235Martam Construction IncorporatedIDOT
24 APR 202662Y30District 011,008$48.00$75.974Martam Construction IncorporatedIDOT
16 JAN 202662R76District 01997$60.00$75.235D. Construction, Inc.IDOT
16 JAN 202662Y05District 01816$65.00$121.124Martam Construction IncorporatedIDOT
16 JAN 202662Y14District 01559$75.00$107.054D. Construction, Inc.IDOT
16 JAN 202664T05District 02468$98.00$154.002Martin & Company ExcavatingIDOT
16 JAN 202664T96District 02805$62.00$81.504Martin & Company ExcavatingIDOT
16 JAN 202670E65District 051,631$58.22$72.562Sangamo Construction CompanyIDOT
07 NOV 202574B78District 073,986$43.50$50.754C-Hill Civil Contractors, Inc.IDOT
19 SEP 202562Y12District 01656$61.00$129.005Martam Construction IncorporatedIDOT
19 SEP 202562Y13District 011,657$49.00$58.776Martam Construction IncorporatedIDOT
19 SEP 202566295District 03510$60.00$65.002D. Construction, Inc.IDOT
19 SEP 202572286District 067,424$51.46$60.732Freesen, a div of UCM, Inc.IDOT
19 SEP 202572324District 06759$47.43$81.973Freesen, a div of UCM, Inc.IDOT
19 SEP 202572M33District 061,640$61.13$72.062Freesen, a div of UCM, Inc.IDOT
Latest IDOT contracts carrying Br deck scar 3/4

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy