Bridge washing N5 unit price, Illinois
Low bidders on IDOT contracts carried a median of $7,312.50 per EACH for item 59200105, bridge washing n5, over the 24 months to 18 SEP 2026, across 18 low bids. Half of all 62 bids fell between $6,093.75 and $12,300.
- Owner
- Illinois DOT
- Item
- 59200105
- Unit
- EACH
- Latest letting
- 12 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 8 | 8 | $10,512 | 21 | $10,822 |
| 2022 | 9 | 9 | $9,600.00 | 25 | $11,337 |
| 2023 | 2 | 2 | $30,000 | 5 | $26,800 |
| 2024 | 9 | 9 | $8,000.00 | 24 | $10,000 |
| 2025 | 9 | 9 | $6,025.00 | 33 | $9,025.00 |
| 2026 | 9 | 9 | $7,500.00 | 29 | $8,800.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 4 | $9,547.00 |
| 1 to 1 | 5 | $5,350.00 |
| 1 to 1 | 4 | $8,397.00 |
| 1 to 1 | 5 | $7,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 JUN 2026 | 76U81 | District 08 | 1 | $24,000 | $54,500 | 2 | M & M Concrete, Inc. | IDOT |
| 27 FEB 2026 | 64V11 | District 02 | 1 | $4,300.00 | $7,150.00 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 27 FEB 2026 | 64V13 | District 02 | 1 | $4,500.00 | $6,825.00 | 4 | M & M Concrete, Inc. | IDOT |
| 27 FEB 2026 | 64V14 | District 02 | 1 | $6,300.00 | $5,375.00 | 4 | All States Painting, Inc. | IDOT |
| 27 FEB 2026 | 64V15 | District 02 | 1 | $7,500.00 | $6,750.00 | 4 | Interstate Maintenance, Incorporated | IDOT |
| 27 FEB 2026 | 68K11 | District 04 | 1 | $82,000 | $82,000 | 1 | All States Painting, Inc. | IDOT |
| 16 JAN 2026 | 64V09 | District 02 | 1 | $9,669.00 | $13,500 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 16 JAN 2026 | 64V10 | District 02 | 1 | $7,125.00 | $7,812.50 | 4 | All States Painting, Inc. | IDOT |
| 16 JAN 2026 | 72047 | District 06 | 1 | $18,300 | $16,400 | 2 | All States Painting, Inc. | IDOT |
| 07 MAR 2025 | 64U07 | District 02 | 1 | $4,550.00 | $9,500.00 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 07 MAR 2025 | 64U09 | District 02 | 1 | $5,350.00 | $8,150.00 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 07 MAR 2025 | 64U10 | District 02 | 1 | $4,875.00 | $6,000.00 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 07 MAR 2025 | 64U11 | District 02 | 1 | $6,025.00 | $6,487.50 | 4 | Pressure Washing Unlimited Inc. | IDOT |
| 17 JAN 2025 | 64T35 | District 02 | 1 | $6,000.00 | $8,212.50 | 4 | All States Painting, Inc. | IDOT |
| 17 JAN 2025 | 64T39 | District 02 | 1 | $9,025.00 | $10,013 | 4 | Pressure Washing Unlimited Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.