Conc fdn ty d unit price, Illinois

Low bidders on IDOT contracts carried a median of $1,292.50 per LF for item 87800200, conc fdn ty d, over the 24 months to 18 SEP 2026, across 24 low bids. Half of all 65 bids fell between $986.49 and $1,485.00.

Owner
Illinois DOT
Item
87800200
Unit
LF
Latest letting
31 JUL 2026
$1,292.50Low bidder's median, per LF
$1,237.50Median of all bids, per LF
24Contracts in the window

By year of letting

Conc fdn ty d, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202111$879.003$879.00
20221414$808.9040$804.40
20231414$923.0035$1,020.00
202455$1,200.0015$1,187.20
20251010$1,402.2826$1,335.08
20261313$1,160.0035$1,164.50
Conc fdn ty d, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Conc fdn ty d, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 017$1,164.5026$1,207.25
District 088$1,397.5020$1,302.50
District 024$904.0011$861.00
Conc fdn ty d, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Conc fdn ty d, IDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
2 to 36$1,843.75
3 to 46$1,361.11
4 to 76$1,358.75
8 to 246$1,000.79
Conc fdn ty d, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Conc fdn ty d
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202662J64District 018$1,164.50$1,182.254Peter Baker & Son Co.IDOT
12 JUN 202662U72District 018$1,015.09$1,010.505Martam Construction IncorporatedIDOT
12 JUN 202676U38District 0824$1,100.00$1,100.001Gerstner Electric, Inc.IDOT
12 JUN 202697827District 083$4,725.00$4,862.463Hank's Excavating & Landscaping, Inc.IDOT
12 JUN 202697903District 083$1,510.00$1,415.002Gerstner Electric, Inc.IDOT
24 APR 202662P51District 018$958.57$958.573Martam Construction IncorporatedIDOT
24 APR 202674E31District 077$1,500.00$1,500.001Bodine Electric of DecaturIDOT
24 APR 202680C85District 0112$986.49$986.494Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc.IDOT
27 FEB 202664J38District 023$787.50$808.752Civil Constructors, Inc. d/b/a/ Helm CivilIDOT
27 FEB 202685790District 023$1,017.00$1,017.001Davenport Electric Contract CompanyIDOT
27 FEB 202697872District 083$1,160.00$1,160.003DMS Contracting, Inc.IDOT
16 JAN 202662D34District 014$1,300.00$1,300.004Lorig Construction CompanyIDOT
16 JAN 202676A46District 083$1,627.50$1,613.752Keller Construction, Inc.IDOT
07 NOV 202585785District 0212$861.00$840.506Gensini Excavating, Inc.IDOT
13 JUN 202576K74District 086$951.77$951.773Keeley & Sons, Inc. Keller Construction Inc.IDOT
Latest IDOT contracts carrying Conc fdn ty d

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy