Conc median surf rem unit price, Illinois
Low bidders on IDOT contracts carried a median of $7.75 per SF for item X4402020, conc median surf rem, over the 24 months to 18 SEP 2026, across 20 low bids. Half of all 45 bids fell between $2.45 and $13.20.
- Owner
- Illinois DOT
- Item
- X4402020
- Unit
- SF
- Latest letting
- 12 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 17 | 17 | $5.00 | 58 | $5.00 |
| 2022 | 12 | 12 | $5.89 | 31 | $5.61 |
| 2023 | 12 | 12 | $9.00 | 28 | $7.90 |
| 2024 | 7 | 7 | $9.25 | 14 | $6.05 |
| 2025 | 11 | 11 | $7.85 | 27 | $4.00 |
| 2026 | 9 | 9 | $7.66 | 18 | $5.12 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 06 | 6 | $9.36 | 11 | $7.66 |
| District 04 | 3 | $2.67 | 10 | $2.96 |
| District 09 | 3 | $25.55 | 8 | $14.66 |
| District 08 | 3 | $7.85 | 6 | $8.93 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 8 to 222 | 5 | $11.05 |
| 234 to 407 | 5 | $25.55 |
| 454 to 2,866 | 5 | $2.67 |
| 2,880 to 26,600 | 5 | $5.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 JUN 2026 | 68K19 | District 04 | 76 | $13.75 | $13.75 | 1 | Gunther Construction, a div of UCM, Inc. | IDOT |
| 12 JUN 2026 | 72491 | District 06 | 2,646 | $2.45 | $2.45 | 3 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 12 JUN 2026 | 72J41 | District 06 | 77 | $11.05 | $11.05 | 1 | W. L. Miller Company | IDOT |
| 24 APR 2026 | 80B21 | District 01 | 4,679 | $5.00 | $4.50 | 3 | K-Five Construction Corporation | IDOT |
| 27 FEB 2026 | 68J46 | District 04 | 459 | $2.67 | $3.24 | 4 | Otto Baum Company, Inc. | IDOT |
| 27 FEB 2026 | 70F37 | District 05 | 981 | $5.25 | $5.25 | 1 | Stark Excavating, Inc. | IDOT |
| 27 FEB 2026 | 72989 | District 06 | 8 | $74.52 | $75.60 | 3 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 27 FEB 2026 | 78A87 | District 09 | 282 | $32.50 | $32.50 | 1 | F. W. Electric, Inc. | IDOT |
| 16 JAN 2026 | 72G90 | District 06 | 222 | $7.66 | $7.66 | 1 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 01 AUG 2025 | 76M55 | District 08 | 2,880 | $7.85 | $5.42 | 2 | Keeley & Sons, Inc. | IDOT |
| 13 JUN 2025 | 64S51 | District 02 | 234 | $10.00 | $10.00 | 1 | Rock Road Companies, Inc. | IDOT |
| 13 JUN 2025 | 72263 | District 06 | 26,600 | $2.74 | $3.02 | 2 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 13 JUN 2025 | 78B06 | District 09 | 276 | $25.55 | $28.02 | 2 | Brown Electric, Inc. | IDOT |
| 25 APR 2025 | 70991 | District 05 | 132 | $4.00 | $7.97 | 2 | Cross Construction, Inc. | IDOT |
| 07 MAR 2025 | 72321 | District 06 | 407 | $13.20 | $13.20 | 1 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.