Deck slab rep (fd-T1) unit price, Illinois
Low bidders on IDOT contracts carried a median of $2,079.93 per SY for item Z0016001, deck slab rep (fd-t1), over the 24 months to 18 SEP 2026, across 56 low bids. Half of all 129 bids fell between $1,675.28 and $3,000.00.
- Owner
- Illinois DOT
- Item
- Z0016001
- Unit
- SY
- Latest letting
- 27 FEB 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 37 | 37 | $1,750.00 | 137 | $2,075.00 |
| 2022 | 33 | 33 | $1,820.00 | 87 | $2,000.00 |
| 2023 | 46 | 46 | $2,016.49 | 137 | $2,600.00 |
| 2024 | 56 | 56 | $2,500.00 | 167 | $2,715.55 |
| 2025 | 39 | 39 | $1,980.00 | 86 | $1,971.58 |
| 2026 | 3 | 3 | $2,769.62 | 7 | $2,769.62 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 07 | 14 | $2,490.36 | 37 | $2,230.74 |
| District 06 | 10 | $1,502.59 | 26 | $1,676.62 |
| District 02 | 7 | $1,650.00 | 18 | $1,700.00 |
| District 08 | 9 | $4,490.00 | 16 | $3,995.00 |
| District 01 | 3 | $1,700.00 | 11 | $2,000.00 |
| District 03 | 7 | $2,000.00 | 10 | $1,900.00 |
| District 05 | 4 | $3,297.31 | 7 | $3,200.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3.20 | 14 | $2,579.81 |
| 4 to 6 | 14 | $2,107.45 |
| 6.40 to 15 | 14 | $2,281.94 |
| 15 to 150 | 14 | $1,808.13 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 FEB 2026 | 76T66 | District 08 | 15 | $2,990.00 | $2,990.00 | 1 | Keeley & Sons, Inc. and Wissehr Electric, Inc. JV | IDOT |
| 16 JAN 2026 | 64T96 | District 02 | 1 | $900.00 | $2,375.00 | 4 | Martin & Company Excavating | IDOT |
| 16 JAN 2026 | 70E65 | District 05 | 3.20 | $2,769.62 | $2,631.69 | 2 | Sangamo Construction Company | IDOT |
| 07 NOV 2025 | 74B78 | District 07 | 38 | $1,700.00 | $1,850.00 | 4 | C-Hill Civil Contractors, Inc. | IDOT |
| 19 SEP 2025 | 66295 | District 03 | 10 | $1,550.00 | $1,675.00 | 2 | D. Construction, Inc. | IDOT |
| 19 SEP 2025 | 72286 | District 06 | 6 | $2,014.89 | $1,807.45 | 2 | Freesen, a div of UCM, Inc. | IDOT |
| 19 SEP 2025 | 74164 | District 07 | 100 | $677.00 | $1,800.00 | 3 | Sangamo Construction Company | IDOT |
| 19 SEP 2025 | 74D09 | District 07 | 4 | $3,580.00 | $3,580.00 | 3 | C-Hill Civil Contractors, Inc. | IDOT |
| 19 SEP 2025 | 74D11 | District 07 | 12.90 | $2,083.17 | $2,199.09 | 2 | Sangamo Construction Company | IDOT |
| 19 SEP 2025 | 76U51 | District 08 | 10 | $4,490.00 | $6,645.00 | 2 | Keeley & Sons, Inc. | IDOT |
| 01 AUG 2025 | 72949 | District 06 | 5 | $1,500.00 | $3,147.00 | 2 | County Contractors, Inc. | IDOT |
| 01 AUG 2025 | 76U45 | District 08 | 15 | $4,490.00 | $6,245.00 | 2 | Keeley & Sons, Inc. | IDOT |
| 13 JUN 2025 | 64T98 | District 02 | 3 | $750.00 | $1,475.00 | 2 | Martin & Company Excavating | IDOT |
| 13 JUN 2025 | 64T99 | District 02 | 1 | $2,000.00 | $2,100.00 | 2 | Martin & Company Excavating | IDOT |
| 13 JUN 2025 | 66H59 | District 03 | 2 | $6,500.00 | $6,500.00 | 1 | Iroquois Paving Corporation | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.