Erosion contr blanket unit price, Illinois

Low bidders on IDOT contracts carried a median of $2.00 per SY for item 25100630, erosion contr blanket, over the 24 months to 18 SEP 2026, across 325 low bids. Half of all 1,093 bids fell between $1.40 and $3.50.

Owner
Illinois DOT
Item
25100630
Unit
SY
Latest letting
18 SEP 2026
$2.00Low bidder's median, per SY
$2.00Median of all bids, per SY
325Contracts in the window

By year of letting

Erosion contr blanket, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2021128127$1.50549$1.50
2022160160$1.84513$1.75
2023124123$2.00398$1.93
2024146146$2.00464$1.79
2025155155$2.00511$2.00
2026131131$2.26448$2.21
Erosion contr blanket, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Erosion contr blanket, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 01135$1.65576$1.60
District 0353$2.20142$2.01
District 0231$1.71108$1.97
District 0939$2.1592$2.15
District 0824$3.0869$3.20
District 0418$2.6245$2.22
District 0710$2.0328$2.06
District 0510$2.6619$2.02
District 065$2.1014$2.05
Erosion contr blanket, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Erosion contr blanket, IDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
8 to 77381$5.00
782 to 2,20381$2.50
2,206 to 6,25881$1.80
6,258 to 170,30982$1.50
Erosion contr blanket, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Erosion contr blanket
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202666926District 033,910$1.84$1.752D. Construction, Inc.IDOT
18 SEP 202666M67District 032,477$2.20$2.203D. Construction, Inc.IDOT
18 SEP 202668E86District 041,443$2.20$2.003Stark Excavating, Inc.IDOT
18 SEP 202668H60District 041,106$4.23$3.524Otto Baum Company, Inc.IDOT
18 SEP 202674650District 07168$2.38$2.253Sangamo Construction CompanyIDOT
18 SEP 202678990District 09764$2.50$2.562Samron Midwest Contracting, Inc.IDOT
18 SEP 202678B55District 09105$2.50$6.802Samron Midwest Contracting, Inc.IDOT
18 SEP 202697892District 081,468$3.65$4.083Plocher Construction Company, Inc.IDOT
31 JUL 202646951District 058,889$2.00$2.002Feutz Contractors, Inc.IDOT
31 JUL 202661K85District 017,128$1.40$1.4010Plote Construction, Inc.IDOT
31 JUL 202661M40District 01427$2.80$3.483Home Towne Electric, Inc.IDOT
31 JUL 202662W20District 0116,065$1.21$1.306D. Construction, Inc.IDOT
31 JUL 202662Y20District 01306$4.00$4.005Martam Construction IncorporatedIDOT
31 JUL 202666N23District 031,740$1.50$1.603Riber Construction, Inc.IDOT
31 JUL 202670G29District 0528,474$1.25$1.453Stark Excavating, Inc.IDOT
Latest IDOT contracts carrying Erosion contr blanket

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy