Fac in exist cab unit price, Illinois
Low bidders on IDOT contracts carried a median of $10,850 per EACH for item X8570215, fac in exist cab, over the 24 months to 18 SEP 2026, across 22 low bids. Half of all 54 bids fell between $7,423.75 and $12,919.
- Owner
- Illinois DOT
- Item
- X8570215
- Unit
- EACH
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 7 | 7 | $4,178.00 | 30 | $4,867.50 |
| 2022 | 6 | 6 | $5,903.50 | 17 | $7,195.90 |
| 2023 | 12 | 12 | $8,688.44 | 21 | $8,339.35 |
| 2024 | 7 | 7 | $10,570 | 19 | $10,570 |
| 2025 | 10 | 10 | $10,564 | 16 | $11,053 |
| 2026 | 11 | 11 | $11,674 | 36 | $11,163 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 5 | $7,153.92 |
| 1 to 2 | 6 | $11,931 |
| 2 to 6 | 5 | $10,907 |
| 6 to 67 | 6 | $11,794 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 61M10 | District 01 | 5 | $13,035 | $13,035 | 1 | K-Five Construction Corporation | IDOT |
| 31 JUL 2026 | 61M13 | District 01 | 1 | $7,285.00 | $7,285.00 | 6 | Dunnet Bay Construction Company | IDOT |
| 31 JUL 2026 | 62J64 | District 01 | 1 | $12,301 | $13,026 | 4 | Peter Baker & Son Co. | IDOT |
| 31 JUL 2026 | 62W91 | District 01 | 2 | $12,959 | $13,300 | 3 | H & H Electric Co. | IDOT |
| 12 JUN 2026 | 62W82 | District 01 | 32 | $11,914 | $11,914 | 3 | H & H Electric Co. | IDOT |
| 12 JUN 2026 | 62W83 | District 01 | 6 | $12,139 | $12,069 | 4 | H & H Electric Co. | IDOT |
| 12 JUN 2026 | 80C89 | District 01 | 56 | $11,674 | $13,287 | 2 | H & H Electric Co. | IDOT |
| 24 APR 2026 | 62K33 | District 01 | 1 | $10,794 | $10,047 | 4 | Plote Construction, Inc. | IDOT |
| 24 APR 2026 | 62L85 | District 01 | 1 | $6,495.04 | $6,673.64 | 2 | K-Five Construction Corporation | IDOT |
| 27 FEB 2026 | 62W92 | District 01 | 5 | $10,907 | $11,281 | 4 | Helm Electric Facility Solutions, Inc. d/b/a Helm Electric | IDOT |
| 27 FEB 2026 | 72989 | District 06 | 1 | $7,153.92 | $7,257.60 | 3 | Illinois Valley Paving, a div of UCM, Inc. | IDOT |
| 07 NOV 2025 | 61L21 | District 01 | 2 | $15,163 | $15,032 | 2 | H & H Electric Co. | IDOT |
| 19 SEP 2025 | 62W89 | District 01 | 11 | $10,059 | $10,059 | 1 | Meade Inc. | IDOT |
| 01 AUG 2025 | 62W57 | District 01 | 2 | $12,800 | $12,800 | 1 | Hecker and Company, Inc. | IDOT |
| 13 JUN 2025 | 62N39 | District 01 | 6 | $10,460 | $15,230 | 2 | Meade Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.