Hma base cse 8 unit price, Illinois
Low bidders on IDOT contracts carried a median of $89.00 per SY for item 35501316, hma base cse 8, over the 24 months to 18 SEP 2026, across 59 low bids. Half of all 244 bids fell between $68.00 and $125.62.
- Owner
- Illinois DOT
- Item
- 35501316
- Unit
- SY
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 26 | 26 | $52.50 | 135 | $56.50 |
| 2022 | 25 | 25 | $87.00 | 94 | $91.50 |
| 2023 | 19 | 19 | $70.68 | 60 | $83.00 |
| 2024 | 30 | 30 | $81.33 | 115 | $78.47 |
| 2025 | 32 | 32 | $89.50 | 132 | $87.82 |
| 2026 | 21 | 20 | $94.00 | 83 | $89.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 3 to 51 | 14 | $165.00 |
| 53 to 112 | 15 | $108.30 |
| 120 to 667 | 15 | $75.00 |
| 793 to 7,747 | 15 | $69.13 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 62L58 | District 01 | 55 | $225.00 | $158.00 | 4 | Builders Paving, LLC | IDOT |
| 18 SEP 2026 | 62W73 | District 01 | 7 | $195.00 | $225.00 | 3 | Peter Baker & Son Co. | IDOT |
| 18 SEP 2026 | 66M67 | District 03 | 232 | $50.00 | $136.47 | 3 | D. Construction, Inc. | IDOT |
| 31 JUL 2026 | 62T84 | District 01 | 125 | $89.00 | $155.40 | 3 | D. Construction, Inc. | IDOT |
| 12 JUN 2026 | 62L30 | District 01 | 1,991 | $50.00 | $61.00 | 6 | D. Construction, Inc. | IDOT |
| 12 JUN 2026 | 62U72 | District 01 | 7,747 | $78.25 | $74.20 | 5 | Martam Construction Incorporated | IDOT |
| 12 JUN 2026 | 62X52 | District 01 | 6 | n/a | $961.43 | 3 | D. Construction, Inc. | IDOT |
| 12 JUN 2026 | 66M92 | District 03 | 139 | $79.00 | $79.00 | 5 | Iroquois Paving Corporation | IDOT |
| 12 JUN 2026 | 72J41 | District 06 | 793 | $103.95 | $103.95 | 1 | W. L. Miller Company | IDOT |
| 24 APR 2026 | 62P51 | District 01 | 802 | $69.13 | $69.13 | 3 | Martam Construction Incorporated | IDOT |
| 24 APR 2026 | 80B09 | District 01 | 120 | $70.00 | $70.00 | 3 | Builders Paving, LLC | IDOT |
| 24 APR 2026 | 80B27 | District 01 | 208.30 | $99.00 | $89.50 | 4 | Plote Construction, Inc. | IDOT |
| 24 APR 2026 | 80B39 | District 01 | 8.90 | $237.27 | $230.00 | 3 | K-Five Construction Corporation | IDOT |
| 24 APR 2026 | 80C85 | District 01 | 6,751 | $100.35 | $92.67 | 4 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 27 FEB 2026 | 62V09 | District 01 | 95 | $150.00 | $65.00 | 4 | Plote Construction, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.