Hma driveway pavt 3 unit price, Illinois
Low bidders on IDOT contracts carried a median of $37.00 per SY for item Z0004510, hma driveway pavt 3, over the 24 months to 18 SEP 2026, across 7 low bids. Half of all 38 bids fell between $37.00 and $70.86.
- Owner
- Illinois DOT
- Item
- Z0004510
- Unit
- SY
- Latest letting
- 17 JAN 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 4 | 4 | $39.25 | 33 | $33.00 |
| 2022 | 9 | 9 | $50.00 | 51 | $50.00 |
| 2023 | 10 | 10 | $51.00 | 39 | $56.00 |
| 2024 | 14 | 14 | $50.50 | 66 | $56.00 |
| 2025 | 3 | 3 | $37.00 | 17 | $44.34 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 01 | 33 | $50.00 | 182 | $50.00 |
| District 02 | 3 | $40.00 | 10 | $42.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 50 | 10 | $65.00 |
| 50 to 130 | 10 | $53.00 |
| 160 to 420 | 10 | $40.48 |
| 512 to 2,003 | 10 | $30.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 JAN 2025 | 61J63 | District 01 | 48 | $58.00 | $39.00 | 7 | Martam Construction Incorporated | IDOT |
| 17 JAN 2025 | 61L00 | District 01 | 215 | $35.00 | $36.78 | 5 | Curran Contracting Company | IDOT |
| 17 JAN 2025 | 61L04 | District 01 | 19 | $37.00 | $80.00 | 5 | K-Five Construction Corporation | IDOT |
| 08 NOV 2024 | 61J87 | District 01 | 163 | $40.97 | $60.00 | 7 | IHC Construction Companies LLC and Curran Contracting Company JV | IDOT |
| 08 NOV 2024 | 61K74 | District 01 | 709 | $29.00 | $45.25 | 5 | A Lamp Concrete Contractors, Inc. | IDOT |
| 08 NOV 2024 | 87869 | District 03 | 205 | $25.00 | $34.00 | 3 | D. Construction, Inc. | IDOT |
| 20 SEP 2024 | 61K63 | District 01 | 130 | $72.00 | $74.90 | 6 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 02 AUG 2024 | 61K51 | District 01 | 280 | $65.00 | $60.50 | 2 | Peter Baker & Son Co. | IDOT |
| 14 JUN 2024 | 89845 | District 04 | 26 | $80.00 | $230.00 | 5 | Centennial Contractors of the Quad Cities, Inc. | IDOT |
| 26 APR 2024 | 61J08 | District 01 | 420 | $36.00 | $33.00 | 4 | Austin Tyler Construction, Inc. | IDOT |
| 26 APR 2024 | 61K33 | District 01 | 114 | $56.00 | $56.00 | 3 | K-Five Construction Corporation | IDOT |
| 26 APR 2024 | 61K34 | District 01 | 2,003 | $41.00 | $55.10 | 3 | Lenny Hoffman Excavating, Inc. | IDOT |
| 08 MAR 2024 | 61J65 | District 01 | 105 | $56.00 | $52.61 | 6 | Plote Construction, Inc. | IDOT |
| 08 MAR 2024 | 61K20 | District 01 | 525 | $51.00 | $51.00 | 3 | Peter Baker & Son Co. | IDOT |
| 08 MAR 2024 | 61K27 | District 01 | 183 | $50.00 | $73.45 | 8 | Triggi Construction, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.