Maint lighting sys unit price, Illinois
Low bidders on IDOT contracts carried a median of $1,372.00 per CAL MO for item Z0033028, maint lighting sys, over the 24 months to 18 SEP 2026, across 20 low bids. Half of all 81 bids fell between $850.00 and $3,121.01.
- Owner
- Illinois DOT
- Item
- Z0033028
- Unit
- CAL MO
- Latest letting
- 07 MAR 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 18 | 18 | $832.00 | 97 | $883.60 |
| 2022 | 27 | 25 | $1,065.10 | 132 | $1,122.97 |
| 2023 | 31 | 31 | $1,575.00 | 114 | $1,680.00 |
| 2024 | 36 | 35 | $1,806.19 | 119 | $1,920.00 |
| 2025 | 8 | 8 | $1,305.00 | 35 | $1,280.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CAL MO) | Low bids | Low-bid median |
|---|---|---|
| 2 to 6 | 5 | $1,600.00 |
| 8 to 10 | 5 | $1,200.00 |
| 10 to 15 | 5 | $2,000.00 |
| 15 to 30 | 5 | $4,880.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 MAR 2025 | 62P43 | District 01 | 18 | $6,150.00 | $6,103.76 | 7 | Lorig Construction Company | IDOT |
| 17 JAN 2025 | 61J91 | District 01 | 10 | $1,310.00 | $1,310.00 | 1 | Geneva Construction Company | IDOT |
| 17 JAN 2025 | 61K07 | District 01 | 9 | $1,434.00 | $1,280.00 | 4 | Schroeder Asphalt Services, Inc. | IDOT |
| 17 JAN 2025 | 61K68 | District 01 | 16 | $720.59 | $690.30 | 4 | Martam Construction Incorporated | IDOT |
| 17 JAN 2025 | 61K86 | District 01 | 9 | $1,300.00 | $925.00 | 4 | Schroeder Asphalt Services, Inc. | IDOT |
| 17 JAN 2025 | 61K87 | District 01 | 8 | $1,025.00 | $1,171.79 | 8 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 17 JAN 2025 | 61L08 | District 01 | 5 | $1,280.00 | $1,280.00 | 3 | Plote Construction, Inc. | IDOT |
| 17 JAN 2025 | 62T41 | District 01 | 2 | $11,000 | $11,500 | 4 | Martam Construction Incorporated | IDOT |
| 08 NOV 2024 | 61J87 | District 01 | 30 | $592.40 | $592.00 | 7 | IHC Construction Companies LLC and Curran Contracting Company JV | IDOT |
| 08 NOV 2024 | 61J90 | District 01 | 10 | $600.00 | $600.00 | 3 | A Lamp Concrete Contractors, Inc. | IDOT |
| 08 NOV 2024 | 62W30 | District 01 | 11 | $4,090.00 | $3,645.00 | 4 | Dunnet Bay Construction Company | IDOT |
| 08 NOV 2024 | 62W38 | District 01 | 25 | $4,880.00 | $4,880.00 | 4 | Judlau Contracting, Inc. | IDOT |
| 20 SEP 2024 | 61G80 | District 01 | 6 | $1,600.00 | $1,500.00 | 7 | Martam Construction Incorporated | IDOT |
| 20 SEP 2024 | 61K60 | District 01 | 15 | $2,560.00 | $2,560.00 | 2 | Capitol Cement Co., Inc. | IDOT |
| 20 SEP 2024 | 61K70 | District 01 | 8 | $1,200.00 | $1,200.00 | 4 | A Lamp Concrete Contractors, Inc. | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.