Maint lighting systm unit price, Illinois

Low bidders on IDOT contracts carried a median of $1,518.80 per CAL MO for item X8000003, maint lighting systm, over the 24 months to 18 SEP 2026, across 53 low bids. Half of all 253 bids fell between $1,022.00 and $2,956.10.

Owner
Illinois DOT
Item
X8000003
Unit
CAL MO
Latest letting
18 SEP 2026
$1,518.80Low bidder's median, per CAL MO
$1,800.00Median of all bids, per CAL MO
54Contracts in the window

By year of letting

Maint lighting systm, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20252424$1,955.00117$1,800.00
20263029$1,449.60136$1,800.00
Maint lighting systm, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Maint lighting systm, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0149$1,523.00242$1,865.00
District 024$791.4111$428.10
Maint lighting systm, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Maint lighting systm, IDOT: low bidder's median by quantity band
Quantity (CAL MO)Low bidsLow-bid median
1 to 613$1,500.00
7 to 1213$1,279.44
12 to 1813$1,489.20
18 to 3614$2,574.20
Maint lighting systm, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Maint lighting systm
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202661M10District 019$841.80$841.801K-Five Construction CorporationIDOT
31 JUL 202661M13District 0118n/a$906.001Dunnet Bay Construction CompanyIDOT
31 JUL 202662J64District 0112$720.00$735.004Peter Baker & Son Co.IDOT
31 JUL 202662W20District 0112$825.00$1,492.366D. Construction, Inc.IDOT
12 JUN 202661M51District 014$4,268.86$4,268.863Martam Construction IncorporatedIDOT
12 JUN 202662R61District 0130$5,390.01$4,700.003OHLA Central, Inc.IDOT
12 JUN 202662U72District 0124$2,535.60$2,524.145Martam Construction IncorporatedIDOT
12 JUN 202662W99District 0118$5,164.50$20,0005K-Five Construction CorporationIDOT
12 JUN 202664V40District 028$3,977.00$3,977.001Valley Construction Co.IDOT
24 APR 202661L48District 0112$546.41$523.202William Charles Construction Company, LLCIDOT
24 APR 202661L84District 014$910.00$910.007K-Five Construction CorporationIDOT
27 FEB 202661M20District 013$146.30$500.005H & H Electric Co.IDOT
27 FEB 202661M21District 013$146.30$500.005H & H Electric Co.IDOT
27 FEB 202661M26District 0116$750.00$788.274A Lamp Concrete Contractors, Inc.IDOT
27 FEB 202661M27District 017$693.96$4,310.006A Lamp Concrete Contractors, Inc.IDOT
Latest IDOT contracts carrying Maint lighting systm

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy