P hma sc il-9.5 e N70 unit price, Illinois

Low bidders on IDOT contracts carried a median of $130.00 per TON for item 40604172, p hma sc il-9.5 e n70, over the 24 months to 18 SEP 2026, across 45 low bids. Half of all 181 bids fell between $116.00 and $256.00.

Owner
Illinois DOT
Item
40604172
Unit
TON
Latest letting
18 SEP 2026
$130.00Low bidder's median, per TON
$150.00Median of all bids, per TON
45Contracts in the window

By year of letting

P hma sc il-9.5 e N70, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20214343$88.50192$95.60
20223030$115.00112$115.00
20232020$142.5684$146.00
20242525$137.00107$186.00
20251818$129.5067$148.95
20262121$127.7582$133.60
P hma sc il-9.5 e N70, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

P hma sc il-9.5 e N70, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0139$127.75169$148.95
District 043$183.605$250.00
P hma sc il-9.5 e N70, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

P hma sc il-9.5 e N70, IDOT: low bidder's median by quantity band
Quantity (TON)Low bidsLow-bid median
26 to 9111$380.00
104 to 73511$156.00
740 to 3,73211$125.00
4,085 to 16,36412$110.75
P hma sc il-9.5 e N70, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying P hma sc il-9.5 e N70
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202662X84District 018,902$145.00$132.203K-Five Construction CorporationIDOT
12 JUN 202662L30District 014,728$113.00$131.456D. Construction, Inc.IDOT
12 JUN 202662R61District 01620$146.94$146.943OHLA Central, Inc.IDOT
12 JUN 202668K18District 043,732$183.60$183.601R. A. Cullinan and Son, a div of UCM, Inc.IDOT
12 JUN 202676U76District 0860$387.60$383.802Keeley & Sons, Inc.IDOT
12 JUN 202680B28District 015,597$121.00$121.005K-Five Construction CorporationIDOT
12 JUN 202680C48District 012,055$121.90$173.952Peter Baker & Son Co.IDOT
24 APR 202662L85District 01751$130.00$135.502K-Five Construction CorporationIDOT
24 APR 202662Y30District 0176$600.00$600.004Martam Construction IncorporatedIDOT
24 APR 202680B12District 01450$127.75$149.382Alliance Contractors, Inc.IDOT
24 APR 202680B30District 014,468$125.00$115.005K-Five Construction CorporationIDOT
24 APR 202680B39District 018,225$116.24$116.243K-Five Construction CorporationIDOT
27 FEB 202662P01District 0143$170.00$165.004Austin Tyler Construction, Inc.IDOT
27 FEB 202662V43District 017,637$88.00$94.002Builders Paving, LLCIDOT
27 FEB 202662Y17District 0177$310.08$397.506MYS, IncorporatedIDOT
Latest IDOT contracts carrying P hma sc il-9.5 e N70

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.