Paint pvt mk line 6 unit price, Illinois

Low bidders on IDOT contracts carried a median of $2.00 per LF for item 78001130, paint pvt mk line 6, over the 24 months to 18 SEP 2026, across 75 low bids. Half of all 221 bids fell between $0.50 and $7.00.

Owner
Illinois DOT
Item
78001130
Unit
LF
Latest letting
31 JUL 2026
$2.00Low bidder's median, per LF
$2.25Median of all bids, per LF
75Contracts in the window

By year of letting

Paint pvt mk line 6, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20215151$0.40153$0.89
20224040$0.7391$1.25
20232828$1.0565$0.72
20242929$0.3277$0.48
20254141$1.50119$2.67
20262828$2.0092$2.02
Paint pvt mk line 6, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Paint pvt mk line 6, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0319$1.0067$1.85
District 0819$0.9544$2.15
District 028$1.5037$1.50
District 048$1.5622$1.96
District 097$1.8417$2.00
District 065$3.9210$4.17
District 054$8.108$8.15
District 073$8.947$9.00
Paint pvt mk line 6, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Paint pvt mk line 6, IDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
7 to 23218$3.00
237 to 60519$5.50
777 to 7,52419$1.84
7,848 to 2,533,64019$0.25
Paint pvt mk line 6, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Paint pvt mk line 6
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202666N23District 03313$2.05$2.053Riber Construction, Inc.IDOT
31 JUL 202666T13District 031,810$13.00$13.001Advanced Asphalt CompanyIDOT
31 JUL 202676V11District 083,500$2.00$1.503Kinney Contractors, Inc.IDOT
31 JUL 202676V21District 08123,619$0.15$0.172Evergreen Roadworks, LLCIDOT
31 JUL 202676V22District 0847,660$0.25$0.252DMS Contracting, Inc.IDOT
12 JUN 202661M51District 0152$1.98$1.983Martam Construction IncorporatedIDOT
12 JUN 202666M92District 03113$4.00$1.855Iroquois Paving CorporationIDOT
12 JUN 202678A85District 097,848$0.43$0.422E. T. Simonds Construction CompanyIDOT
12 JUN 202685794District 021,716$1.50$1.405Centennial Contractors of the Quad Cities, Inc.IDOT
12 JUN 202689864District 04286$7.50$6.384Phoenix Corporation of the Quad CitiesIDOT
12 JUN 202697827District 08320$6.30$6.483Hank's Excavating & Landscaping, Inc.IDOT
12 JUN 202697896District 08598$9.00$9.003Stutz Excavating, Inc.IDOT
24 APR 202646671District 0320,000$0.30$0.305RoadSafe Traffic Systems, Inc.IDOT
24 APR 202666T58District 0325,432$0.25$0.375Complete Asphalt Service Co.IDOT
24 APR 202668K54District 042,533,640$0.11$0.124Varsity Striping & Construction Co.IDOT
Latest IDOT contracts carrying Paint pvt mk line 6

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.