Pipe underdr t 2 6 unit price, Illinois

Low bidders on IDOT contracts carried a median of $30.28 per LF for item 60108206, pipe underdr t 2 6, over the 24 months to 18 SEP 2026, across 25 low bids. Half of all 81 bids fell between $22.50 and $50.10.

Owner
Illinois DOT
Item
60108206
Unit
LF
Latest letting
18 SEP 2026
$30.28Low bidder's median, per LF
$31.00Median of all bids, per LF
25Contracts in the window

By year of letting

Pipe underdr t 2 6, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202155$40.0029$34.00
202277$20.0021$24.60
20231515$23.0057$19.50
20241414$30.6447$31.00
20251212$23.9536$29.15
202655$26.0015$36.00
Pipe underdr t 2 6, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Pipe underdr t 2 6, IDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 0115$31.0058$31.00
District 026$20.2417$26.00
District 054$39.406$40.45
Pipe underdr t 2 6, IDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Pipe underdr t 2 6, IDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
37 to 4676$33.95
500 to 1,7586$52.00
3,400 to 7,1386$24.00
7,768 to 36,2957$14.48
Pipe underdr t 2 6, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Pipe underdr t 2 6
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 SEP 202664V52District 021,758$26.00$55.003Civil Constructors, Inc. d/b/a/ Helm CivilIDOT
12 JUN 202670D62District 05230$36.00$43.352William Charles Construction Company, LLCIDOT
27 FEB 202664R72District 027,768$26.00$29.642Civil Constructors, Inc. d/b/a/ Helm CivilIDOT
16 JAN 202662F94District 0117,182$14.00$18.143D. Construction, Inc.IDOT
16 JAN 202662K62District 01587$55.00$55.005F. H. Paschen, S.N. Nielsen & Associates LLCIDOT
07 NOV 202562R63District 011,146$36.00$55.006Dunnet Bay Construction CompanyIDOT
19 SEP 202562R22District 0121,306$13.25$31.783D. Construction, Inc.IDOT
01 AUG 202564C24District 0236,295$14.48$22.505OHLA Central, Inc.IDOT
01 AUG 202564U52District 02310$10.00$90.003G. M. Sipes Construction, Inc.IDOT
01 AUG 202591653District 058,480$42.80$42.801Rowe Construction, a div of UCM, Inc.IDOT
25 APR 202564N98District 026,584$13.30$20.003William Charles Construction Company, LLCIDOT
07 MAR 202562N91District 016,048$35.00$25.003Dunnet Bay Construction Company & K-Five Construction CorporationIDOT
07 MAR 202564N01District 02467$38.00$38.001Civil Constructors, Inc. d/b/a/ Helm CivilIDOT
17 JAN 202561J25District 013,400$16.00$22.904P. T. Ferro Construction Co.IDOT
17 JAN 202561K07District 01500$61.50$44.004Schroeder Asphalt Services, Inc.IDOT
Latest IDOT contracts carrying Pipe underdr t 2 6

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy