Selective clearing unit price, Illinois
Low bidders on IDOT contracts carried a median of $500.00 per UNIT for item Z0064800, selective clearing, from 15 JAN 2021 to 02 AUG 2024, across 79 low bids. Half of all 320 bids fell between $345.00 and $800.00.
- Owner
- Illinois DOT
- Item
- Z0064800
- Unit
- UNIT
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 23 | 23 | $400.00 | 120 | $400.00 |
| 2022 | 23 | 23 | $510.00 | 82 | $470.00 |
| 2023 | 26 | 26 | $615.00 | 95 | $640.00 |
| 2024 | 7 | 7 | $325.00 | 23 | $440.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (UNIT) | Low bids | Low-bid median |
|---|---|---|
| 0.52 to 4 | 19 | $2,000.00 |
| 4 to 14 | 20 | $372.50 |
| 15 to 43 | 20 | $400.00 |
| 45 to 445 | 20 | $423.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 62K73 | District 01 | 56 | $300.00 | $400.00 | 2 | Lorig Construction Company | IDOT |
| 14 JUN 2024 | 60J10 | District 01 | 1 | $900.00 | $900.00 | 3 | IHC Construction Companies, L.L.C. | IDOT |
| 14 JUN 2024 | 62F11 | District 01 | 4 | $850.00 | $884.00 | 3 | Judlau Contracting, Inc. | IDOT |
| 14 JUN 2024 | 62R41 | District 01 | 159 | $250.00 | $259.20 | 4 | Gallagher Asphalt Corporation | IDOT |
| 14 JUN 2024 | 62U83 | District 01 | 4 | $325.00 | $382.50 | 2 | Dunnet Bay Construction Company | IDOT |
| 26 APR 2024 | 60P75 | District 01 | 11 | $300.00 | $307.50 | 6 | R. W. Dunteman Company | IDOT |
| 26 APR 2024 | 62L16 | District 01 | 5 | $450.00 | $450.00 | 3 | Peter Baker & Son Co. | IDOT |
| 17 NOV 2023 | 62T18 | District 01 | 2 | $800.00 | $800.00 | 7 | Lorig Construction Company | IDOT |
| 17 NOV 2023 | 62T36 | District 01 | 30 | $350.00 | $350.00 | 5 | Lorig Construction Company | IDOT |
| 17 NOV 2023 | 62T57 | District 01 | 28 | $660.00 | $660.00 | 3 | D. Construction, Inc. | IDOT |
| 17 NOV 2023 | 62W14 | District 01 | 55 | $750.00 | $1,100.00 | 3 | Clean Cut Tree Service, Inc. | IDOT |
| 22 SEP 2023 | 62U61 | District 01 | 24.20 | $640.00 | $645.00 | 2 | Homer Tree Service, Inc. | IDOT |
| 22 SEP 2023 | 62V19 | District 01 | 84 | $650.00 | $650.00 | 3 | McGinty Bros., Inc. | IDOT |
| 04 AUG 2023 | 62R18 | District 01 | 5 | $600.00 | $600.00 | 3 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | IDOT |
| 04 AUG 2023 | 62T05 | District 01 | 1.50 | $2,200.00 | $2,000.00 | 7 | MYS, Incorporated | IDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.
How these prices were read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.