Term fiber in cabinet unit price, Illinois

Low bidders on IDOT contracts carried a median of $203.50 per EACH for item X1400217, term fiber in cabinet, over the 24 months to 18 SEP 2026, across 32 low bids. Half of all 119 bids fell between $150.60 and $414.14.

Owner
Illinois DOT
Item
X1400217
Unit
EACH
Latest letting
31 JUL 2026
$203.50Low bidder's median, per EACH
$252.00Median of all bids, per EACH
32Contracts in the window

By year of letting

Term fiber in cabinet, IDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202144$235.9021$298.00
202255$167.0018$180.70
202388$168.7028$168.70
20241313$180.0042$178.20
20251111$176.1134$240.00
20261717$250.0068$252.00
Term fiber in cabinet, IDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Term fiber in cabinet, IDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
2 to 88$520.29
8 to 368$258.30
36 to 968$203.50
120 to 4,2008$106.50
Term fiber in cabinet, IDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest IDOT contracts carrying Term fiber in cabinet
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 JUL 202661K85District 018$252.00$252.0010Plote Construction, Inc.IDOT
31 JUL 202661M13District 012$3,413.00$3,413.006Dunnet Bay Construction CompanyIDOT
31 JUL 202661M40District 0178$192.00$192.003Home Towne Electric, Inc.IDOT
31 JUL 202662W91District 0112$180.00$132.003H & H Electric Co.IDOT
12 JUN 202662U72District 0156$188.19$187.345Martam Construction IncorporatedIDOT
12 JUN 202662W99District 01360$93.77$135.005K-Five Construction CorporationIDOT
12 JUN 202697903District 082$555.00$847.502Gerstner Electric, Inc.IDOT
24 APR 202662K33District 012$180.00$157.504Plote Construction, Inc.IDOT
24 APR 202662P51District 0112$187.20$187.203Martam Construction IncorporatedIDOT
24 APR 202662Y28District 01288$69.25$84.622Meade Inc.IDOT
27 FEB 202662R19District 014,200$68.26$74.752Meade Inc.IDOT
27 FEB 202662W92District 0112$424.50$399.754Helm Electric Facility Solutions, Inc. d/b/a Helm ElectricIDOT
16 JAN 202661M02District 0136$264.60$350.003H & H Electric Co.IDOT
16 JAN 202662P93District 0136$250.00$250.005Triggi Construction, Inc.IDOT
16 JAN 202662W47District 013$6,600.00$6,375.004D. Construction, Inc.IDOT
Latest IDOT contracts carrying Term fiber in cabinet

Filter this item by your own quantity, district and period, or check your price against it, in the IDOT explorer.

How these prices were read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are IDOT's own: this item is compared with IDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy