Bridge deck, remove existing concrete overlay unit price, Indiana
Low bidders on INDOT contracts carried a median of $14.00 per SYS for item 722-12463, bridge deck, remove existing concrete overlay, over the 24 months to 05 NOV 2026, across 15 low bids. Half of all 58 bids fell between $11.00 and $25.86.
- Owner
- Indiana DOT
- Item
- 722-12463
- Unit
- SYS
- Latest letting
- 06 AUG 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 19 | 19 | $17.37 | 55 | $20.00 |
| 2023 | 14 | 14 | $15.50 | 49 | $17.29 |
| 2024 | 21 | 21 | $15.00 | 79 | $16.00 |
| 2025 | 9 | 9 | $16.00 | 32 | $18.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Crawfordsville | 5 | $17.13 | 21 | $20.00 |
| Vincennes | 3 | $24.00 | 13 | $24.00 |
| Fort Wayne | 4 | $12.50 | 11 | $14.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SYS) | Low bids | Low-bid median |
|---|---|---|
| 136 to 677 | 3 | $50.00 |
| 678 to 988 | 4 | $22.00 |
| 1,026 to 1,167 | 4 | $10.45 |
| 1,450 to 2,088 | 4 | $10.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 06 AUG 2025 | R-41781-A | Greenfield | 1,108 | $9.50 | $19.25 | 6 | GRADEX INC | INDOT |
| 06 AUG 2025 | B-43795-A | Fort Wayne | 1,450 | $14.00 | $13.82 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 12 MAR 2025 | B-43976-A | Vincennes | 1,159 | $16.00 | $16.00 | 3 | RAGLE, INC. | INDOT |
| 26 FEB 2025 | R-38912-A | Greenfield | 1,167 | $9.90 | $12.00 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 12 FEB 2025 | B-43418-A | Crawfordsville | 790 | $20.00 | $20.00 | 5 | E & B PAVING LLC | INDOT |
| 12 FEB 2025 | B-43441-A | Crawfordsville | 677 | $17.13 | $19.56 | 2 | SUPERIOR CONSTRUCTION CO INC | INDOT |
| 12 FEB 2025 | B-45633-A | Fort Wayne | 678 | $10.00 | $15.00 | 2 | MILESTONE CONTRACTORS LP | INDOT |
| 15 JAN 2025 | B-42175-A | Vincennes | 887 | $24.00 | $25.00 | 5 | CLR INC | INDOT |
| 15 JAN 2025 | B-45568-A | Fort Wayne | 136 | $50.00 | $50.00 | 3 | E & B PAVING LLC | INDOT |
| 11 DEC 2024 | B-39043-A | LaPorte | 1,745 | $10.00 | $14.05 | 4 | SUPERIOR CONSTRUCTION CO INC | INDOT |
| 11 DEC 2024 | B-42764-A | Crawfordsville | 1,026 | $11.00 | $11.00 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 14 NOV 2024 | B-43239-A | Vincennes | 988 | $24.75 | $24.75 | 5 | BLANKENBERGER BROTHERS INC | INDOT |
| 14 NOV 2024 | B-43313-A | Fort Wayne | 2,088 | $11.00 | $11.00 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 14 NOV 2024 | B-43434-A | Crawfordsville | 1,927 | $9.10 | $11.54 | 5 | FORCE CONSTRUCTION CO INC | INDOT |
| 14 NOV 2024 | B-44936-A | Crawfordsville | 201 | $100.00 | $65.67 | 6 | E & B PAVING LLC | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way