Conduit, steel, galvanized, 2 in. unit price, Indiana

Low bidders on INDOT contracts carried a median of $41.94 per LFT for item 807-06592, conduit, steel, galvanized, 2 in., over the 24 months to 05 NOV 2026, across 36 low bids. Half of all 154 bids fell between $35.00 and $53.25.

Owner
Indiana DOT
Item
807-06592
Unit
LFT
Latest letting
07 MAY 2026
$41.94Low bidder's median, per LFT
$41.00Median of all bids, per LFT
36Contracts in the window

By year of letting

Conduit, steel, galvanized, 2 in., INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221919$37.1059$35.00
20233838$37.5594$37.95
20243535$41.30126$42.00
20252424$42.10111$41.00
202699$35.0032$36.50
Conduit, steel, galvanized, 2 in., INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Conduit, steel, galvanized, 2 in., INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Greenfield7$40.0044$40.00
Fort Wayne7$55.0029$50.00
Seymour7$43.2026$43.20
LaPorte7$42.8825$42.88
Crawfordsville4$47.5017$35.00
Vincennes4$28.5013$45.00
Conduit, steel, galvanized, 2 in., INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Conduit, steel, galvanized, 2 in., INDOT: low bidder's median by quantity band
Quantity (LFT)Low bidsLow-bid median
10 to 1029$60.00
102 to 3149$37.00
386 to 9949$50.00
1,505 to 14,3039$30.00
Conduit, steel, galvanized, 2 in., INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Conduit, steel, galvanized, 2 in.
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
07 MAY 2026R-44001-BLaPorte935$31.00$31.003MILESTONE CONTRACTORS LPINDOT
15 APR 2026R-46095-AVincennes206$30.00$60.003RAGLE, INC.INDOT
08 APR 2026R-42595-ASeymour1,598$30.00$35.004CRIDER & CRIDER, INC.INDOT
11 MAR 2026M-45652-ALaPorte100$44.00$197.002MIDWESTERN ELECTRIC LLCINDOT
11 FEB 2026R-41527-ASeymour150$102.00$56.504DAN CRISTIANI EXCAVATING CO INCINDOT
11 FEB 2026R-43393-AGreenfield386$53.50$53.504RIETH-RILEY CONSTRUCTION CO., INC.INDOT
11 FEB 2026R-43599-ACrawfordsville207$35.00$35.007E & B PAVING LLCINDOT
11 FEB 2026R-45152-AVincennes2,437$20.50$28.003RAGLE, INC/E & B PAVING LLC J/VINDOT
14 JAN 2026B-43431-CCrawfordsville57$95.51$95.512BEATY CONSTRUCTION INCINDOT
10 DEC 2025R-43621-AGreenfield217$37.00$36.008HIS CONSTRUCTORS INCINDOT
10 DEC 2025B-42319-AGreenfield102$44.00$40.009PONTEM CONTRACTORS INCINDOT
10 DEC 2025B-43742-AFort Wayne20$100.00$100.006E & B PAVING LLCINDOT
13 NOV 2025T-42907-BSeymour580$20.00$26.004HUMMEL ELECTRIC, INC.INDOT
08 OCT 2025T-43988-BCrawfordsville102$60.00$57.502EDWARD & JONES CONCRETE INCINDOT
08 OCT 2025TM-46164-ASeymour25$55.00$55.001MIDWESTERN ELECTRIC LLCINDOT
Latest INDOT contracts carrying Conduit, steel, galvanized, 2 in.

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy