Low bidders on INDOT contracts carried a median of $47.00 per LFT for item 605-06090, curb, integral concrete, over the 24 months to 05 NOV 2026, across 27 low bids. Half of all 126 bids fell between $34.25 and $64.97.
- Owner
- Indiana DOT
- Item
- 605-06090
- Unit
- LFT
- Latest letting
- 07 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 18 | 18 | $44.08 | 53 | $45.75 |
| 2023 | 9 | 9 | $75.00 | 22 | $77.50 |
| 2024 | 18 | 18 | $48.89 | 54 | $49.14 |
| 2025 | 14 | 14 | $48.00 | 60 | $46.00 |
| 2026 | 11 | 11 | $46.00 | 56 | $51.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Greenfield | 11 | $47.00 | 70 | $43.17 |
| LaPorte | 5 | $46.00 | 17 | $54.00 |
| Seymour | 3 | $60.00 | 13 | $60.00 |
| Crawfordsville | 3 | $54.00 | 10 | $26.50 |
| Vincennes | 3 | $28.00 | 9 | $44.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LFT) | Low bids | Low-bid median |
|---|---|---|
| 4 to 55 | 6 | $72.22 |
| 60 to 235 | 7 | $45.00 |
| 258 to 471 | 7 | $49.00 |
| 504 to 4,867 | 7 | $30.79 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | R-43918-A | LaPorte | 4,867 | $30.79 | $30.79 | 3 | F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLC | INDOT |
| 07 OCT 2026 | R-44109-A | LaPorte | 258 | $46.00 | $48.69 | 4 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 11 MAR 2026 | R-43981-A | Vincennes | 19 | $79.00 | $92.00 | 2 | MILESTONE CONTRACTORS LP | INDOT |
| 11 MAR 2026 | R-44024-A | Greenfield | 471 | $53.00 | $40.17 | 6 | E & B PAVING LLC | INDOT |
| 11 MAR 2026 | R-44130-A | Greenfield | 311 | $61.19 | $61.19 | 11 | OLCO INC | INDOT |
| 11 FEB 2026 | R-41527-A | Seymour | 320 | $41.00 | $41.00 | 4 | DAN CRISTIANI EXCAVATING CO INC | INDOT |
| 11 FEB 2026 | R-41916-A | Crawfordsville | 4 | $65.45 | $65.45 | 3 | HIS CONSTRUCTORS INC | INDOT |
| 11 FEB 2026 | R-43476-A | Greenfield | 470 | $34.00 | $34.00 | 7 | E & B PAVING LLC | INDOT |
| 11 FEB 2026 | R-45152-A | Vincennes | 762 | $26.75 | $45.00 | 3 | RAGLE, INC/E & B PAVING LLC J/V | INDOT |
| 11 FEB 2026 | B-46167-A | LaPorte | 20 | $105.00 | $105.00 | 3 | SUPERIOR CONSTRUCTION CO INC | INDOT |
| 14 JAN 2026 | R-42755-A | Greenfield | 63 | $36.00 | $59.12 | 10 | CALUMET CIVIL CONTRACTORS INC | INDOT |
| 10 DEC 2025 | R-42000-A | Fort Wayne | 289 | $49.00 | $51.75 | 4 | HRP CONSTRUCTION INC | INDOT |
| 10 DEC 2025 | R-42808-A | Vincennes | 85 | $28.00 | $35.50 | 4 | RAGLE, INC. | INDOT |
| 10 DEC 2025 | R-43621-A | Greenfield | 157 | $47.00 | $45.50 | 8 | HIS CONSTRUCTORS INC | INDOT |
| 10 DEC 2025 | B-43917-A | LaPorte | 28 | $100.00 | $76.00 | 5 | SUPERIOR CONSTRUCTION CO INC | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way