Low bidders on INDOT contracts carried a median of $1,174.78 per EACH for item 202-97009, fire hydrant assembly, remove, over the 24 months to 05 NOV 2026, across 18 low bids. Half of all 63 bids fell between $913.33 and $1,750.00.

Owner
Indiana DOT
Item
202-97009
Unit
EACH
Latest letting
07 MAY 2026
$1,174.78Low bidder's median, per EACH
$1,100.00Median of all bids, per EACH
18Contracts in the window

By year of letting

Fire hydrant assembly, remove, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221010$1,370.0032$1,053.72
202388$950.0026$1,040.00
202477$1,000.0019$1,000.00
202588$2,221.0934$1,720.00
202688$1,057.0024$1,011.00
Fire hydrant assembly, remove, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Fire hydrant assembly, remove, INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
LaPorte7$1,090.0023$1,069.98
Vincennes6$1,016.0018$1,051.00
Fire hydrant assembly, remove, INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Fire hydrant assembly, remove, INDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 14$1,335.50
1 to 45$1,032.00
4 to 54$1,721.09
7 to 125$1,090.00
Fire hydrant assembly, remove, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Fire hydrant assembly, remove
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
07 MAY 2026R-44001-BLaPorte8$1,090.00$1,090.003MILESTONE CONTRACTORS LPINDOT
15 APR 2026R-43995-AVincennes12$1,082.00$1,082.003JBI CONSTRUCTION INCINDOT
11 FEB 2026R-41916-ACrawfordsville3$1,259.56$1,000.003HIS CONSTRUCTORS INCINDOT
11 FEB 2026R-43813-AFort Wayne9$1,720.00$872.003E & B PAVING LLCINDOT
11 FEB 2026R-43979-AVincennes2$1,032.00$1,091.002E & B PAVING LLCINDOT
11 FEB 2026R-45152-AVincennes5$750.00$1,070.003RAGLE, INC/E & B PAVING LLC J/VINDOT
14 JAN 2026R-40648-ALaPorte1$824.00$824.004MILESTONE CONTRACTORS LPINDOT
14 JAN 2026R-43470-AVincennes7$1,000.00$1,000.003BLANKENBERGER BROTHERS INCINDOT
10 DEC 2025R-42000-AFort Wayne4$1,500.00$1,500.004HRP CONSTRUCTION INCINDOT
10 DEC 2025R-42808-AVincennes1$1,750.00$1,240.004RAGLE, INC.INDOT
13 NOV 2025R-42797-AGreenfield5$5,523.79$2,697.508OLCO INCINDOT
07 MAY 2025R-35981-ALaPorte9$2,833.25$1,324.164F H PASCHEN S N NIELSEN & ASSOCIATES LLCINDOT
07 MAY 2025R-43589-ALaPorte1$921.00$921.002MILESTONE CONTRACTORS LPINDOT
07 MAY 2025B-41844-ALaPorte4$2,639.35$1,854.664F H PASCHEN S N NIELSEN & ASSOCIATES LLCINDOT
07 MAY 2025B-41850-ALaPorte4$1,942.17$1,720.004F H PASCHEN S N NIELSEN & ASSOCIATES LLCINDOT
Latest INDOT contracts carrying Fire hydrant assembly, remove

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy