Mailbox assembly, double unit price, Indiana

Low bidders on INDOT contracts carried a median of $390.00 per EACH for item 611-06498, mailbox assembly, double, over the 24 months to 05 NOV 2026, across 14 low bids. Half of all 66 bids fell between $375.00 and $540.73.

Owner
Indiana DOT
Item
611-06498
Unit
EACH
Latest letting
08 APR 2026
$390.00Low bidder's median, per EACH
$405.00Median of all bids, per EACH
14Contracts in the window

By year of letting

Mailbox assembly, double, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221818$325.0054$325.00
20231313$393.1231$393.12
202477$475.0019$425.00
202599$380.0051$400.00
202644$387.5012$411.50
Mailbox assembly, double, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Mailbox assembly, double, INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Greenfield6$375.0032$387.50
Fort Wayne4$550.0016$547.65
Mailbox assembly, double, INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Mailbox assembly, double, INDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 13$375.00
1 to 34$479.00
3 to 33$402.00
3 to 64$387.50
Mailbox assembly, double, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Mailbox assembly, double
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
08 APR 2026R-42521-ACrawfordsville6$400.00$400.004RIETH-RILEY CONSTRUCTION CO., INC.INDOT
11 MAR 2026R-43940-AGreenfield2$375.00$543.504WILLIAM CHARLES CONSTRUCTION COMPANYINDOT
11 MAR 2026R-44374-AGreenfield3$375.00$375.001E & B PAVING LLCINDOT
11 FEB 2026R-42006-AFort Wayne3$402.00$525.003C & E EXCAVATING INCINDOT
10 DEC 2025R-42000-AFort Wayne1$550.00$550.004HRP CONSTRUCTION INCINDOT
10 DEC 2025R-43621-AGreenfield3$375.00$350.008HIS CONSTRUCTORS INCINDOT
10 DEC 2025B-40311-ASeymour5$375.00$375.006MILESTONE CONTRACTORS LPINDOT
08 OCT 2025R-41153-AFort Wayne3$550.00$522.656HRP CONSTRUCTION INCINDOT
12 MAR 2025R-39270-AGreenfield1$408.00$527.004MILESTONE CONTRACTORS LPINDOT
12 MAR 2025R-41437-ALaPorte4$615.00$615.003RIETH-RILEY CONSTRUCTION CO., INC.INDOT
15 JAN 2025R-41302-AGreenfield1$375.00$440.009MILESTONE CONTRACTORS LPINDOT
15 JAN 2025R-45107-AGreenfield1$365.00$365.006E & B PAVING LLCINDOT
15 JAN 2025R-45584-ASeymour1$380.00$380.005E & B PAVING LLCINDOT
14 NOV 2024B-42769-AFort Wayne3$586.00$586.003MILESTONE CONTRACTORS LPINDOT
11 SEP 2024R-43287-AFort Wayne1$796.43$798.214BROOKS CONSTRUCTION COMPANY INCINDOT
Latest INDOT contracts carrying Mailbox assembly, double

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy