Mulched seeding r unit price, Indiana

Low bidders on INDOT contracts carried a median of $2.42 per SYS for item 621-06559, mulched seeding r, from 12 JAN 2022 to 10 MAY 2023, across 237 low bids. Half of all 653 bids fell between $1.48 and $4.50.

Owner
Indiana DOT
Item
621-06559
Unit
SYS
Latest letting
10 MAY 2023
$2.42Low bidder's median, per SYS
$2.45Median of all bids, per SYS
237Contracts in the window

By year of letting

Mulched seeding r, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2022148148$2.42436$2.42
20238989$2.50217$2.50
Mulched seeding r, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Mulched seeding r, INDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Seymour55$1.75191$2.00
Crawfordsville47$2.32122$2.31
LaPorte42$2.76116$2.60
Fort Wayne39$3.5084$3.60
Vincennes30$2.6278$2.50
Greenfield21$1.8253$2.66
Mulched seeding r, INDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Mulched seeding r, INDOT: low bidder's median by quantity band
Quantity (SYS)Low bidsLow-bid median
6 to 50059$7.00
500 to 1,45859$2.66
1,473 to 3,08059$2.00
3,114 to 331,15660$1.35
Mulched seeding r, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Mulched seeding r
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
10 MAY 2023R-41423-BLaPorte1,074$3.00$3.001TEMPLE & TEMPLE EXCAVATING & PAVING INCINDOT
10 MAY 2023R-41592-BCrawfordsville6,429$6.00$6.001TEMPLE & TEMPLE EXCAVATING & PAVING INCINDOT
10 MAY 2023R-43807-BLaPorte171$8.40$8.401RIETH RILEY CONSTRUCTIONINDOT
10 MAY 2023B-38038-CGreenfield56$7.55$7.551BEATY CONSTRUCTION INCINDOT
10 MAY 2023B-41458-BSeymour2,924$0.40$1.353FORCE CONSTRUCTION CO INCINDOT
10 MAY 2023B-41626-ACrawfordsville2,411$2.10$2.104FORCE CONSTRUCTION CO INCINDOT
10 MAY 2023B-42266-BGreenfield747$2.66$2.832BEATY CONSTRUCTION INCINDOT
10 MAY 2023B-43839-ALaPorte347$5.55$5.551RIETH RILEY CONSTRUCTIONINDOT
10 MAY 2023T-42602-BCrawfordsville11,278$1.72$1.162MILESTONE CONTRACTORS LPINDOT
19 APR 2023B-41440-ALaPorte1,409$1.04$1.043SUPERIOR CONSTRUCTION CO INCINDOT
12 APR 2023R-42753-AVincennes3,114$0.80$0.802E & B PAVING LLCINDOT
12 APR 2023R-42938-ACrawfordsville, Greenfield155$20.55$20.553RIETH RILEY CONSTRUCTIONINDOT
12 APR 2023R-42970-ALaPorte893$3.05$3.052RIETH RILEY CONSTRUCTIONINDOT
12 APR 2023R-43860-ALaPorte174$9.80$9.802MILESTONE CONTRACTORS NORTH INCINDOT
12 APR 2023R-44068-AGreenfield50,895$0.85$0.842C-TECH CORPORATION INCINDOT
Latest INDOT contracts carrying Mulched seeding r

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy